IPE-TM-510 Hydraulics
IPE-TM-510-16
This procedure provides Inflection Point Engineering practice and guidelines for the hydraulic calculations and the generation of the process hydraulics reports
The hydraulics are not based on a unit specific plot plan but a typical plot plan layout. This is necessary because during the Schedule A design the final plot plan, piping lengths and layout are not yet known. Equivalent line lengths are not exact but determined from a combination of standard factors and specified nozzle elevations. The Contractor is responsible for verifying that the system hydraulics represented in the project specifications are adequate and must adjust them as necessary for the final plot layout, piping arrangement, and actual equipment purchased.
The Process Hydraulics can be used by the Contractor for their initial hydraulic estimates; however, they are not intended to take the place of the Contractor’s final hydraulics. Modification of the hydraulics to be consistent with the “as built” units and the final hydraulic check of equipment is the Contractor’s responsibility.
| Normal Flow Scenario | Always 100% |
|---|---|
| Pressure Drop (piping and velocity related equipment) | Pressure drops for the Design and Alternate flow scenarios are based on the ratio of flow rates, densities and viscosities. For multiple process cases, the non-governing normal case pressure drop will be recalculated to reflect the pressure drop in relation to the governing case. |
| Elevation | If the P&ID indicates “Free Draining” downstream of the equipment, then elevate the equipment to have the material flow downward in the outlet pipe. If the P&ID indicates “Locate on platform as close to inlet nozzle as possible”, then make the equipment elevation the same as the inlet nozzle elevation with the pipe close coupled. |
| Minimum Liquid Level | The distance from the point defined for elevation to the minimum liquid level, typically 0.5 ft. The 0.5 ft value is set based on most vertical vessels having the lower level connection 6” from the bottom tangent and the height of the vortex beaker in a horizontal vessel of 6”. Use 0.5 ft for horizontal vessels to be more conservative. If a vessel has a LLL greater than 6”, then enter the LLL value instead. This makes sure that any pumps on the vessel outlet do not take credit for any static heads that may not always be there. This approach applies when the liquid is being pumped or pressured from the vessel. For vertical liquid full vessels, use the tangent length. |
|---|---|
| Maximum Liquid Level | Receivers/Hor. Surge Drum = vessel diameter The vessel diameter (more conservative) rather than the max controlled level is used when calculating the pump shutoff pressure. Vertical Surge drums/Liquid Full vessels = tangent length Fractionators/Vertical Product Separator = level range plus distance from bottom tangent to bottom level nozzle (typically level range plus 6”). |
| Actual Elevation | From vessel drawing or P&ID Horizontal: This is the distance from grade to the bottom of the main shell (excluding any water boot). Vertical: The distance from grade to the bottom tangent of the vessel. |
| Section Max DP | Fractionators: The tray/packing pressure drop for each section Receivers, Separators, Surge Drums, KO Drums, Compressor Interstage, Suction Drums: 0 psi |
| Pressure Drop | Horizontal receivers: No frictional pressure drop Fractionators/Trayed Columns/Packed: The frictional pressure drop is constant for all cases. The fractionator pressure drop is primarily a function of tray loadings (which are relatively constant even if the reflux changes) and not proportional to changes in flow to the fractionator. This value should be consistent with the value shown on the 307 and 301 project specifications. Treaters/Reactors (including internals): The frictional pressure drop does vary with flow. Absorbers: The frictional pressure drop is constant for all cases. If the pressure drop is large, consider adjusting the pressure drop with flow. |
| Elevation | Typically at grade, except thermosiphon reboilers. If the pipe from the shell and tube overhead condenser to the overhead receiver has a note on the P&ID saying “Free Draining”, then the elevation should be set 5 ft above the top of the receiver shell. For water cooled condensers, see Procedure IPE-TM-320-02 “Design of Fractionator Condensing Systems” Section 6.10. |
|---|
| Condenser Rundown | If yes, then the static head should be ignored for the Fractionator Overhead condenser mounted above the overhead receiver and an equalization line should be shown on the P&ID. |
|---|---|
| Elevation | Typically at 40 ft. |
| Suction strainer pressure drop | The clean service strainer pressure drop is included in the calculation of the suction piping equivalent length. See Procedure IPE-TM-510-08 Piping Equivalent Length Guidelines. |
|---|---|
| Maximum Pump Suction Pressure | Vessel Set Press + Vessel Press Drop + Max LL + Vessel elevation – Pump CL (Use the highest average SG from all cases) |
| Elevation | Elevation: Typically at grade. Feeds to a column: In many cases, it is difficult to design around slug flow by increasing or decreasing the line size, assuming that we can even predict it with any degree of certainty. Consider placing the control valve at the level of the column inlet flange for flashing fluids. Use T-800-02, “Piping Pressure Drop” to determine the flow regime. This minimizes the velocity and slug flow and hammering in the column inlet line as the fluid rises up the line to the column inlet. |
|---|---|
| Control Valve in Pump Circuit | This is for the minimum pressure drop for the normal case. For multiple process cases, the minimum control valve drop is applied to the governing case for the pump. All other normal cases will have higher control valve pressure drops. The minimum pressure drop is the greater of the following: 25 psi (no lower than 24.5 psi) 50% of circuit friction drop (start to end of circuit, excluding static head and nonfloating CV pressure drop) 10% of pump head or 7% of pump head when differential head is greater than 1000 psi If Cvmax/Cvmin is greater than 8, then consult the process control coordinator (PCC) for standard and enhanced scope projects. If two control valves in parallel are required, P&IDs should indicate two. |
| Inlet Pressure | The design hydraulic pressure at the inlet of the (all liquid stream) valve should be at least 25 psi above the vapor pressure to ensure that the fluid remains all liquid at the valve inlet. |
| Elevation | Typically at grade. |
|---|---|
| Pressure Drop | See IPE-TM-510-01 Permanent Pressure Loss for Primary Flow Elements. |
| Liquid Base Specific Gravity | Base SG = 141.5 / (131.5 + API) To convert from Base SG to Flowing SG, this can be done manually by using the graph in Crane Appendix A-7 titled “Specific Gravity-Temperature Relationship for Petroleum Oils” |
| Normal Flow on Meter, % of Meter Maximum | The default value is 80%. |
| (Transmitter Differential) | See table below This is based on the criteria that process P (psia)/meter range (in H2O) >1 for vapor streams. |
| Beta Ratio | If the beta ratio is outside the acceptable range: For new units, increase the line size to decrease beta ratio For revamps, increase the orifice meter range to decrease beta ratio For revamps, increase the % of meter max to decrease beta ratio |
| Flow Meter Type | Stream Phase | Process Press, psig | in H2O |
|---|---|---|---|
| Venturimeter | Any | Any | 50 |
| Fulltap (Pipetap) orificemeter or Flangetap orifice meter | Liquid | Any | 100 |
| Fulltap (Pipetap) orificemeter or Flangetap orifice meter | Vapor | 10-35 | 25 |
| Fulltap (Pipetap) orificemeter or Flangetap orifice meter | Vapor | >35 | 50 |
| Fulltap (Pipetap) orificemeter or Flangetap orifice meter | Vapor | >85 | 100 |
| Elevation | Typically at grade. |
|---|---|
| Multiple | If there are multiple lines combining into one, Inflection Point Engineering does not know the order that the lines will be combined. Therefore, the flowsheet and hydraulics should just show one node even if the PFD and the P&ID show multiple mix points. If the intermediate lines need to be sized on the P&ID, list the line size after the mix point (based on total flow rate of all streams). |
| Elevation | Typically at grade. |
|---|---|
| Multiple | If there is a single line splitting into multiple lines, Inflection Point Engineering does not know the order that the lines will be split. Therefore, the flowsheet and hydraulics should just show one node even if the PFD and the P&ID show multiple points. If the intermediate lines need to be sized on the P&ID, list the line size before the split point (based on total flow rate of all streams). |
| Line Size | In general, the minimum line size for process lines is 1”. See Procedure IPE-TM-810-02 “Pipe Size Selection” Section 4. |
|---|---|
| Wall Thickness | The defaults are: 2” and smaller Sch. 80 3” to 10” Sch. 40 12” and larger 3/8” wall = 0.375” |
| Roughness | The pipe roughness has a default value of 0.00015 ft. This is the roughness shown on a Moody diagram for smooth commercial pipe. The roughness factor enters into the pressure drop calculation. |
| Static Head Calculation Method | Use a correlation of Lockhart and Martinelli to calculate an effective specific gravity. This effective specific gravity is higher than that obtained by dividing the total flowing pounds by the total flowing volume. Two-phase downflow static head is always ignored. Two-phase upflow: A liquid holdup method from Baker (1958) experimental data is used. See method in |
| Condenser Rundown | If yes, then the static head should be ignored for the Fractionator Overhead condenser mounted above the overhead receiver and an equalization line should be shown on the P&ID. |
| Filter | Set the pressure drops as: Normal/Design/Alternate flow scenarios Dirty /Dirty /Clean |
|---|
| Elevation | Typically at grade. |
|---|
| Design case | We run hydraulics at 110% of normal to account for typical fluctuations in the plant. A real plant will not run constantly at the so-called Steady State conditions of the Process Simulation. |
|---|---|
| Pumped Circuit | If a pump has multiple destinations, then include the pump in all circuits not just the circuit governing the pump head. |
| PIC | Assume that the PIC is located on the vessel (even though it is shown on the piping in the P&ID) when the PIC is associated with controlling the pressure of the vessel. |
|---|
17.1 Use the typical flow scenario factors of 100/110/60 (or 50) as if the unit is new. The customer expects the unit will operate at revamp capacity. Use the typical flow scenario factors to ensure that the unit has flexibility to be controlled at that capacity.
17.2 In a pumped circuit, the control valve normal pressure drop must be greater than 10 psi. Otherwise increase the impeller size or replace the pump. If the control valve design flow scenario pressure drop is less than 10 psi, then discuss this issue at the Hydraulics Review Meeting.
17.3 After the Hydraulics Review Meeting, change the design flow scenario factor for the entire project to 100 so that this case is not included in the EDI or the I-file.
17.4 If Inflection Point Engineering is giving a guarantee on the revamp flow rates:
a. Show the normal and design flow scenarios in the EDI.
b. Ensure that the control valve design pressure drop is greater than 10 psi.
c. Check that the control valve in the pumped circuit satisfies the needs for 50% of the circuit frictional pressure drop. If most of the circuit pressure drop is static head rather than frictional, then the control valve typically can tolerate a lower pressure drop.
The liquid holdup density is calculated as follows:
1. Calculate the pressure drop (psi/100’) in the piping based only on the flow of liquid.
2. Calculate the pressure drop (psi/100’) in the piping based only on the flow of vapor.
3. Interpolate from the following chart to calculate the liquid volume portion based on the square root ratio of liquid-only pressure drop to vapor-only pressure drop.
4. The average composite liquid holdup density is (where ρ=lb/ft³):
| (DPL/DPV)½ | Liquid Volume % |
|---|---|
| 0.0058 | 1.0 |
| 0.01 | 1.55 |
| 0.02 | 2.65 |
| 0.04 | 4.65 |
| 0.1 | 9.4 |
| 0.2 | 15.8 |
| 0.4 | 24.4 |
| 0.7 | 33.0 |
| 1.0 | 38.5 |
| 2.0 | 52.0 |
| 4.0 | 66.0 |
| 7.0 | 78.0 |
| 10.0 | 87.0 |
| 15.5 | 100.0 |
© 2026 Inflection Point Engineering, LLC. All rights reserved. The content of this page — including calculation methods, reference data, written analysis, interactive tools, and source code — is the intellectual property of Inflection Point Engineering, LLC and is protected under applicable copyright, trademark, and trade secret laws. Unauthorized reproduction, redistribution, modification, or derivative use in whole or in part is prohibited without prior written consent.
Disclaimer. This material is provided for informational and educational purposes only and does not constitute professional engineering advice. Calculations, reference data, and methodologies are based on published standards and accepted engineering practice but are not a substitute for engineering judgment, site-specific analysis, or review by a licensed Professional Engineer. Inflection Point Engineering, LLC makes no warranties, express or implied, regarding the accuracy, completeness, or fitness for a particular purpose of any content presented here, and shall not be liable for any direct, indirect, incidental, or consequential damages arising from its use. Users assume all risk associated with applying this content to real-world design, operations, or decisions.
© 2026 Inflection Point Engineering, LLC. All rights reserved.