IPE-TM-320 Fractionation
IPE-TM-320-03
This procedure explains why, where, and how much contingency to add to the design of the Propylene-Propane Splitter Column.
Generally, fractionator contingencies are required to account for the following factors:
Many customers expect additional design margins to provide capacity for future use. For competitive designs, clarify the customer’s philosophy.
The customer receives a guarantee stating that the Oleflex process unit will produce a fixed quantity of propylene, while consuming no more than “X” units of propane per unit of propylene produced. “X” is calculated by taking the yield estimate propane requirement multiplied by a “capacity factor”. The yield estimate of propane consumption accounts for the non-selective conversion of propane to by-products, as well as an estimate of separation inefficiencies. The capacity factor for Oleflex is normally 1.05. The heat and weight balance generated by Inflection Point Engineering includes this “capacity factor” and therefore shows the propylene product quantity at 1.05 times the guaranteed quantity. The Process Specialist should review the capacity factor that is used for each job.
If a C3 Splitter is designed following a Inflection Point Engineering FCC process unit, the feed is usually based on a stream from the Gas Concentration heat and weight balance (Debutanizer net overhead or C3/C4 Splitter net overhead). The recovery of the propylene and propane in the Gas Concentration Unit ranges from 93 to 97%. If the Gas Concentration heat and weight balance is not available when the C3 Splitter is being designed, the feed should be based on 95% of propylene and 97% of propane given in the yield estimate. As no extra feed is assumed to the C3 Splitter the capacity factor for the FCC design is 1.0.
No overage is to be added to the design product purities and/or reflux. The design product purities should be set by the customer and are normally the guarantee values. The design reflux rate is the rate needed to produce the design product purities as determined by tray to tray calculations.
Inflection Point Engineering-TON does the actual tray to tray calculations, using a UNISIM process simulation with a modified Peng-Robinson property package. This package includes modified relative volatilities of propane and propylene based on commercial data. The use of this modified property package will result in a more realistic reflux requirement for a given separation, than would be calculated using standard property packages, and will result in a smaller column diameter. The data which Inflection Point Engineering-TON will provide back to DP includes:
Inflection Point Engineering-DP generates the heat and weight for the column, including the flows associated with the heat pump compressor and reboiler/condenser. Inflection Point Engineering-DP generates the tray loads with the reflux fixed as per section 5.2. These loads are then sent back to Inflection Point Engineering-TON for final sizing of the column’s MD or ECMD trays.
Inflection Point Engineering-TON MD tray design point is equivalent to a conventional tray at 82% of flood. A conventional tray at 82% of jet flood typically has 10% additional useable capacity. Inflection Point Engineering-TON will design a tray with at least 10% additional useable capacity above the design loads.
The Inflection Point Engineering standard design for C3 Splitters is MD trays because it provides for a more cost effective design overall. If valve or sieve tray designs were compared at equal reflux with the MD tray design, the comparative economics will show for the valve or sieve trays - fewer trays, greater column height, larger diameter, and higher column pressure drop.
If the comparison is made at equal column heights, MD trays are often more cost effective than valve or sieve trays because of the ability to have more MD trays per given tangent length, thus resulting in lower utilities, lower internal loads, higher capacity for the same diameter, etc. This type of comparison is typically valid for revamps, where the column height is already fixed.
Note that in this memorandum no attempt has been made to differentiate between MD and ECMD trays. All references to MD would also apply to ECMD trays.
The flow scheme and typical instrumentation used for the Oleflex C3 Splitter is shown on the process flow diagram, Attachment 1.
The design capacity of the condenser, reboiler and compressor should be well matched to the design capacity of the column/trays. As stated in Section 5.4, the trays are to be designed with at least 10% additional useable capacity above the design loads. It is expected that the reboiler, condenser and compressor will have a similar design philosophy, allowing use and benefit from the additional capacity of the trays. This difference is the normal value between a guaranteeable duty and an expected maximum duty. As a result of this no special design case is needed for the reboiler, condenser and compressor.
© 2026 Inflection Point Engineering, LLC. All rights reserved. The content of this page — including calculation methods, reference data, written analysis, interactive tools, and source code — is the intellectual property of Inflection Point Engineering, LLC and is protected under applicable copyright, trademark, and trade secret laws. Unauthorized reproduction, redistribution, modification, or derivative use in whole or in part is prohibited without prior written consent.
Disclaimer. This material is provided for informational and educational purposes only and does not constitute professional engineering advice. Calculations, reference data, and methodologies are based on published standards and accepted engineering practice but are not a substitute for engineering judgment, site-specific analysis, or review by a licensed Professional Engineer. Inflection Point Engineering, LLC makes no warranties, express or implied, regarding the accuracy, completeness, or fitness for a particular purpose of any content presented here, and shall not be liable for any direct, indirect, incidental, or consequential damages arising from its use. Users assume all risk associated with applying this content to real-world design, operations, or decisions.
© 2026 Inflection Point Engineering, LLC. All rights reserved.