Inflection Point Engineering Reference Tables

Process Safety PHA Methods

PHA / risk assessment methods — HAZOP, what-if, FMEA, LOPA, bowtie — comparison and selection guidance.

README

Method Comparison

PHA Method Comparison Matrix

Method Best for Typical life-cycle phase Team size Effort (person-wk) Qualitative/Quant Deliverable Key standard
Checklist Well-understood process replication; small MOC Detailed design, pre-startup, MOC 1-2 0.1-0.5 Qualitative Completed checklist OSHA 3132; CCPS Ch.4
What-If Early concept, bench/pilot, simple units Conceptual, FEL-1 2-4 0.5-2 Qualitative What-if/consequence/safeguards table CCPS Ch.6
HAZOP Continuous flow process, complex units w/ P&IDs FEL-3 design freeze, 5-yr revalidation 5-8 3-12 Qualitative Node deviations w/ C/C/S/R and recs IEC 61882; CCPS Ch.7
LOPA Risk-ranking selected HAZOP scenarios; SIL target Post-HAZOP, pre-SIS design 2-4 (with HAZOP results) 1-3 Semi-quantitative LOPA worksheet w/ IEF, IPL, PFD, residual freq CCPS LOPA 2001; IEC 61511-3
FMEA / FMECA Rotating & electrical equipment reliability Reliability, spares, RCM 3-5 2-6 Qualitative or Semi-quant FMEA sheet w/ RPN or criticality IEC 60812; MIL-STD-1629A
Bowtie Major-accident hazards; communication Risk register, LFL presentation 4-6 1-3 Qualitative Central event + threats + consequences + barriers CCPS Bow Ties 2018
Fault Tree (FTA) Quantification of IEF or PFD; shared-cause SIL verification, major-accident QRA 2-3 2-8 Quantitative Top event probability with cutsets IEC 61025
Event Tree (ETA) Accident progression; QRA consequence tree Facility siting, emergency planning QRA 2-3 1-4 Quantitative Probability-weighted outcome tree IEC 60300-3-9
Preliminary Hazard Analysis (PrHA) Early FEL-1 hazard identification Conceptual / FEL-1 3-5 0.5-2 Qualitative PHL + ranking CCPS Ch.2; MIL-STD-882E
Facility Siting Study Occupied-building vulnerability from blast/fire Site layout; FEL-2 3-5 2-6 Semi-quant Consequence-based siting matrix API RP 752 (2019)

LOPA IPL Credits

Typical LOPA Independent Protection Layer (IPL) PFD Credits

IPL / Safeguard Typical PFD Credit (orders of mag) Notes / Source
BPCS control loop (as safeguard) 1E-1 1 CCPS LOPA 2001 Table 6.5; one BPCS credit per scenario.
Operator response 10+ min with alarm 1E-1 1 CCPS LOPA 2001 Ch.6; independent indication required.
Operator response <10 min 1 0 No credit per CCPS 2001; use only w/ careful HF analysis.
Relief valve (well maintained) 1E-2 2 CCPS LOPA 2001; validated by API 510 inspection.
Rupture disc (properly selected) 1E-2 2 CCPS LOPA; install on clean service.
Blast-resistant control room / barricade 1E-2 2 API 752; facility-siting IPL.
Dike / containment (leak+accumulation) 1E-2 2 For liquid release consequences.
SIS SIL-1 function 1E-1 to 1E-2 1-2 IEC 61511 target range for SIL-1.
SIS SIL-2 function 1E-2 to 1E-3 2-3 IEC 61511; PFD demand mode.
SIS SIL-3 function 1E-3 to 1E-4 3-4 IEC 61511; rare for refinery; fuel-gas burners, H2 crossover.
SIS SIL-4 function 1E-4 to 1E-5 4-5 Rare in process; usually nuclear / aviation.
Fire & Gas detection + shutdown (certified) 1E-1 1 Credit only if independent from BPCS & SIS.
Passive fire protection (PFP, 2h) 1E-2 2 UL 1709 rated; maintenance-dependent.
Deluge / water spray 1E-1 1 NFPA 15; consumption-rate sensitive.

Source: Process_Safety_PHA_Methods_Reference_v1.xlsx