Inflection Point Engineering Section 13 — Electrical

Power System Design Practice

IPE Engineering Practice IPE-EP-13-1-1

Document number: IPE-EP-13-1-1 · Section: 13 — Electrical

1.0

1.1

1.2

1.3

1.4

1.5

1.6

2.0

SCOPE

This Practice provides design preferences of the Owner in the Electrical Power Engineering design for plants and associated facilities.

This Practice, as normally used, will generate and display information required for development of detailed one line diagrams, overall plot plans, and engineered equipment specifications for the power distribution system.

This Practice will be applicable to both new facilities and the modernization of existing facilities.

All Owner Practices are to be used in conjunction with this Practice to provide the complete detail design requirements.

Any deviation from this Practice must be approved by the procedure described in EP 1-1-3. A revision bar indicates all changes made to this Revision.

REFERENCES

The latest published edition of the following Standards and Codes shall be used with this Practice:

STANDARDS AND PUBLICATIONS

IPE Engineering Practices
EP 1-1-1 Explanation and Use of IPE Engineering Practices EP 1-1-3 Deviations to IPE Engineering Practices
EP 13-2-1 Electrical Detail Design and Construction Practice EP 13-2-2 Electrical Equipment Inspection and Testing
EP 13-3-1 Induction Motors 500HP and Below
EP 13-3-2 Induction Motors Above 500HP EP 13-3-3 Synchronous Motors
EP 13-3-4 Induction Motors 500HP and Below Explosion Proof EP 13-4-1 Power Transformers
EP 13-5-1 Low Voltage Switchgear
EP 13-5-2 Medium Voltage Vacuum Switchgear EP 13-6-1 Medium Voltage Motor Controllers EP 13-6-2 Motor Control Centers 600 Volt Class EP 13-8-1 Wire and Cable 600 Volt and Below EP 13-8-2 Power Cable 5KV and Above
EP 13-9-1 Stationary Batteries and Battery Chargers
EP 13-16-1 Electrical Equipment Shelters

STANDARDS AND PUBLICATIONS (Cont.)

2.1 Trade Standards

The Owner is in general agreement with the published standards of API, CMA, and etc. when equipment or system design can be supplied with increased reliability at a minimal cost above Manufacturer's standard. Where increased reliability per dollar spent is questionable based on the Contractor's experience, the Contractor may propose to the Owner for approval of the deletion of the trade standard or parts thereof.

2.2

2.2.1

2.2.2

3.0

3.1

3.2

3.3

3.4

3.5

3.6

3.7

3.8

3.9

3.10

3.11

3.12

3.13

3.14

Owner Practices

IPE Engineering Practices are to be referenced where necessary on the Manufacturer's and/ or Contractor's drawings and specifications, but are not to be retyped or redrawn.

Where IPE Engineering Practices are not available for a particular situation or piece of equipment, the Contractor is to submit his standard or specification to the Owner for approval. Owner approval for material and/or equipment specifications is required before it is issued for procurement.

DEFINITIONS

Coincident Demand (C.D.) - The sum of two or more demands which occur in the same demand interval.

Contractor - Company or business that agrees to furnish materials or perform specified services at a specified price and/or rate to the Owner.

Demand (D) - The electric load at the receiving terminals averaged over a specified interval of time. Demand is expressed in kilowatts, kilovoltamperes or amperes. The interval of time is generally 15 minutes, 30 minutes or one hour.

Demand Factor (D.F.) - The ratio of the maximum demand of a system to the total connected load of the system.

Diversity Factor (DI.F) - The ratio of the maximum demand of two or more loads to their coincident maximum demand for the same time period.

Firm Load - Data is obtained from actual equipment performance characteristics and duty cycles.

Inspector - A Inflection Point Engineering, LLC appointed engineer or inspector.

Load Factor - The ratio of the average load over a designated period of time to the peak load occurring in that same period.

Manufacturer - The recipient of a direct or indirect purchase order for materials and/or equipment. In this context, a direct order is one issued to a Manufacturer by a Contractor or the Owner. An indirect order is one issued to a Manufacturer by a vendor (recipient of a direct order) for materials, fabricated components, or subassemblies.

Maximum Demand (M.D.) - The largest of all demands which have occurred during a specified period of time.

Owner - Inflection Point Engineering, LLC.

Owner's Engineer - A Inflection Point Engineering, LLC appointed engineer.

Peak Load (P.L.) - The maximum load consumed by a unit or group of units in a stated period of time. It may be the maximum instantaneous load or the maximum averaged load over a designated period of time.

Purchaser - The party placing a direct purchase order. The Purchaser is the Owner's designated representative.

BASIC PHILOSOPHY

The following sections describe the general requirements and preferences for the distribution system. In some cases, special design parameters will alter these general requirements as well as require economic and technical evaluation before the final design is approved by the Owner.

The choice of meters, metering system and meter information/data gathering system shall be specified by the Owner. The metering methods described below are for general planning. The specific metering types or systems to be used at a particular facility must be approved by the Owner to insure the sufficiency of the metering and compatibility to existing systems. As a minimum, solid-state metering shall have digital displays and the capability to communicate via IEEE RS 232/485 ports.

When solid state meters are supplied, as a minimum, they shall provide the same metering values and functionality as electro-mechanical/analog meters.

Substation Grounding design shall comply with ANSI/IEEE STD 80 and NFPA 70.

The requirements are similar to critical substations except the system configuration preference is primary selective or looped primary.

Plant distribution grounding design shall comply with ANSI/IEEE Std 80 and Std 142 as well as NFPA 70.

POWER SYSTEM ARRANGEMENT

For Secondary Selective and Primary Selective Substations, there shall be two separate buses with each bus supplying half of the total branch circuit loads, and each bus capable of supplying power to both buses. The Contractor shall be responsible for obtaining specific design requirements for all Secondary Selective and Primary Selective schemes. This shall include but not be limited to such items as automatic transfer schemes, type of switching devices, etc.

Every effort shall be made to duplicate automatic transfer schemes at a facility to reduce confusion for operators (such as written procedures).

Where motors are designated for a given service as: 1) normal and spare; 2) 3-50% rated machines (i.e., two out of three motors normally running or equivalent); or 3) If two or more motors can operate independently for partial service (such as air-cooled heat exchanger fans and parallel cooling water circulation pumps), the following shall apply:

Emergency bus deenergization shall be provided by one of the following means:

ELECTRICAL EQUIPMENT REQUIREMENTS

Alarm contacts shall be provided for the following functions.

+1% accuracy, 250 degree movement, 4-1/4 inch face. Solid state metering with digital displays may be provided instead of analog metering. The solid state meters must provide, as a minimum, the same functions as analog meters and comply with paragraph 4.3.1.10 of this Practice.

These starters shall be supplied with main contact vacuum interrupters, not elecro-mechanical air interrupter contactors.

On brushless synchronous exciter field supplies, the battery bank shall be sized to provide 4 hours of backup with the battery charger off. The battery charger shall be a battery eliminator type. Each battery charger shall be sized to recharge the battery bank after a 4-hour discharge in 8 hours, while simultaneously supplying maximum field current.

6.13 Testing

Electrical equipment shall be given the type of test as indicated in Table 6 and shall require a witness of the test as indicated. All tests shall be witnessed by the Owner unless directed otherwise by the Owner. The required specific test items and methods are detailed in the associated equipment's IPE Engineering Practice and Plant Standard Operating Procedure SOP# 10-0201001 (Section-B Commissioning & Energizing New Electrical Equipment).Table 6

DOCUMENTATION

8.0 TABLES

TABLE 1

NOMINAL SYSTEM VOLTAGES FOR MOTORS

Service Voltage Nameplate Voltage
Non-Critical Motors
below 1/2 HP
120V., 1-Ph, 60Hz 115/230V., 1-Ph, 60Hz
Critical Motors
1/2 HP and below
480V., 3-Ph, 60Hz 230/460V., 3-Ph, 60Hz
1/2 thru 100 HP 480V., 3-Ph, 60Hz 460V., 3-Ph, 60Hz
101 thru 5000 HP 2300V, 4160V., 3-Ph, 60Hz 2300V, 4160V., 3-Ph, 60Hz
Above 5000 HP
(special consideration)
4.16-13.8KV., 3-Ph, 60Hz
(special consideration)
4.16 -13.8KV., 3-Ph, 60Hz

TABLE 2

NOMINAL SYSTEM VOLTAGES FOR LIGHTING

Service Voltage Fixture Voltage
Outdoor General Area and Roadways
(High Pressure Sodium or Metal Halide)
480V., 3-Ph. 60Hz(1) 480V., 1-Ph, 60Hz
Indoor Building High Bay Lighting (Metal Halide) 208/120V., 3-Ph, 60Hz 208V., 1-Ph, 60Hz
Process Area Lighting (High Pressure Sodium or Metal Halide) 208/ 120V., 3-Ph, 60Hz 120V., 1-Ph, 60Hz
General Office and Shop Lighting (Fluorescent) 208/120V., 3-Ph, 60Hz 120V., 1-Ph, 60Hz
Emergency (Incandescent) 208/120V., 3-Ph, 60Hz 120V., 1-Ph, 60Hz

NOTES:

(1) The majority of the Owner's 480 Volt systems are high resistance grounded limiting phase-to-ground current to 5 ampere.

TABLE 3

NOMINAL SYSTEM VOLTAGES FOR RECEPTACLES

Service Voltage Receptacle Voltage
Welding 480V., 3-Ph, 60Hz 480V., 3-Ph, 60Hz
Convenience 120V., 1-Ph, 60Hz 120V., 1-Ph, 60 Hz or
208V., 3-Ph, 60Hz

TABLE 4

BIL RATINGS FOR MEDIUM VOLTAGE AIR BRAKE SWITCHES (para. 6.2.3.1)

Nominal System Voltage BIL Rating
4160 volts and below 60KV
7200 to 13,800 volts 95 KV

TABLE 5

BIL RATINGS FOR MEDIUM VOLTAGE LIQUID IMMERSED SWITCHES (para. 6.2.3.2)

Nominal System Voltage BIL Rating
4160 volts and below 75 KV
7200 to 13,800 volts 110KV

TABLE 6

ELECTRICAL EQUIPMENT TESTING AND WITNESS REQUIREMENTS

Electrical Equipment Testing Required Testing Required Witness Required
Routine Complete
Power Transformers
< 1.5 MVA
1.6 to 7.5 MVA
> 7.5 MVA
X X
X(2)
X (1)
X
X (1)(2)
X
Outdoor Oil/SF6 Breakers X X
Medium Voltage Switchgear X X
Medium Voltage Controllers X X (2)
Low Voltage Switchgear X X (2)
600 Volt Class Motor Control Center X X (2)
480 Volt Pre-fabricated Switchracks X X (2)
NEMA Frame Motors < 200 HP X X (2) X (2)
Large Frame Induction Motors X X (2) X (2)
Synchronous Motors X (2) X X
Bus Duct X X (2)
Neutral Grounding Resistor X X (2)
Medium Voltage Metal Enclosed Switches X X (2)
Medium Voltage Power Cable X X (2)
Low Voltage Power and Control Wire X X (2)
UPS X X (2)
Power Conditioner X X (2)
Low Voltage Automatic
Transfer Switches
X X (2)
Outdoor Equipment Shelters and Assorted Electrical Equipment per EP 13-16-1(3) X (3) X
Stationary Batteries and Chargers X X (2)
Actuators for MOV's X X (2)

NOTES: