Inflection Point Engineering Section 12 — Instruments and Controls

Control Systems

IPE Engineering Practice IPE-EP-12-1-1

Document number: IPE-EP-12-1-1 · Section: 12 — Instruments and Controls

SCOPE

2.0 REFERENCES

The following codes and standards shall be considered as part of this Practice. All documents shall be the latest editions in force on the date of issuance of this Practice.

STANDARDS AND PUBLICATIONS

IPE Engineering Practices IPE Engineering Practices
EP 1–1–3 Deviations to IPE Engineering Practices
EP 5–1–1 General Piping Design
EP 5–1–2 Piping Layout
EP 5–2–3 IPE Piping Standards
EP 5–3–14 Pressure Relief Valves
EP 5–3–17 Control Valves, Actuators and Accessories
EP 5–5–3 Piping Erection and Testing
EP 5–6–8 Steam Tracing
EP 5–6–5 Piping for Instruments
EP 3–7–1 Pressure Relieving Systems
EP 12–1–3 Instrument Enclosures
EP 12–1–6 Primary Temperature Element Assemblies
EP 12–1–13 Magnetic Flowmeters
EP 12–1–14 Turbine Flowmeters
EP 12–1–15 Positive Displacement Flowmeters
EP 12–1–16 Level Displacers
EP 12–1–18 Gage Glasses
EP 12–1–19 Pressure Gauges
EP 12–1–22 Solenoid Valves
EP 12–1–25 Instrument Cable
EP 12–2–1 Control Systems Installations
EP 12–2–2 Site Inspection and Testing of New Instruments
EP 12–3–1 Distributed Control Systems
EP 12–5–1 Programmable Control Equipment
EP 12–6–1 Control Centers

STANDARDS AND PUBLICATIONS (CONT.)

IPE Engineering Practices (Cont.) IPE Engineering Practices (Cont.)
EP 12–7–1 On–Line Analyzers EP 12–7–2 Analyzer Shelters
EP 12–9–1 Instrumentation for Above Ground Storage Tanks EP 12–10–1 Protective Instrumentation Systems
EP 12–10–2 Testing of Protective Instrumentation Systems EP 13–1–1 Power System Design Practices
EP 13–2–1 Electrical Detail Design and Construction Practice EP 13–17–1 Uninterruptible Power Supply
EP 13–18–1 Power Conditioners
EP 14–1–1 Winterization
EP 12–7–1 On–Line Analyzers EP 12–7–2 Analyzer Shelters
EP 12–9–1 Instrumentation for Above Ground Storage Tanks EP 12–10–1 Protective Instrumentation Systems
EP 12–10–2 Testing of Protective Instrumentation Systems EP 13–1–1 Power System Design Practices
EP 13–2–1 Electrical Detail Design and Construction Practice EP 13–17–1 Uninterruptible Power Supply
EP 13–18–1 Power Conditioners
EP 14–1–1 Winterization
API API
RP 551 Manual on Installation of Refinery Instrument and Control Systems 2530 Orifice Metering of Natural Gas
Manual of Petroleum Measurement Standards
RP 551 Manual on Installation of Refinery Instrument and Control Systems 2530 Orifice Metering of Natural Gas
Manual of Petroleum Measurement Standards
ISA ISA
S5.1
S5.4
Instrumentation Symbols and Identification
Instrument Loop Diagrams
SAMA SAMA
PMC 33.1 Electromagnetic Susceptibility of Process Control Instrumentation PMC 33.1 Electromagnetic Susceptibility of Process Control Instrumentation
NFPA NFPA
496
70
Purged and Pressurized Enclosures for Electrical Equipment
National Electric Code
AGA AGA
351 Manual of Petroleum Measurement Standards

DEFINITIONS

CONTRACTOR REQUIREMENTS

The following system shall be used as a guideline for numbering of instruments and their

EXAMPLE: XXX–YYYY

X = LETTER Y= DIGIT

All Process Flow (PFD) and Piping and Instrumentation (P&ID) drawings shall have been agreed upon by the contractor’s Control Systems representative(s) before being submitted to IPE for review.

representative before installation.

EP 12–2–2.

All systems as well as instrumentation on package equipment, shall be subject to inspection by IPE. A quality assurance plan shall be developed itemizing those systems or packages to be inspected in the shop. Frequent quality control inspections may be required by IPE.

The contractor/fabricator shall advise IPE two weeks before functional test and check– out.

DESIGN AND MATERIALS

Control Valves shall conform to EP 5–3–17.

Distributed Control Systems shall meet the requirements of EP 12–3–1.

SYSTEM INSTALLATION

The criteria shown in Table 4 shall be followed during hydrotesting, for protection of instruments.

7.0 TABLES

TABLE 1 RECORDER PEN COLORS

Red Flow
Green Temp or Level
Blue Pressure
Violet Used to avoid second pen conflicts

TABLE 2 ALARM SEQUENCES

Process Normal Light is out and horn is silent
Process Abnormal Light on flashing and horn sounds
Acknowledge Light steady and horn is silenced

TABLE 3

SPARE TUBES REQUIREMENTS

Tubes per Bundle Spare Tubes per Bundle
37 10
19 5
14 4
7 1
4 0

TABLE 4

PROCEDURES FOR PROTECTING INSTRUMENTS DURING HYDROTESTING

Instruments Block
& Vent
Remove Blind
Off
Test Notes
1. Analyzers X
2. Control Valves X
3. Regulators & pressure balanced valves X
4. Flow Instruments—D/P cell & bellows types X
5. Rotameters X (1)
6. Positive Displacement Meters X
7. Turbine Meters X
8. Flow Switches—bellows type X
9. Flow Switches—vane type X
10. Gauge Glasses X
11. Level displacers X
12. Level —D/P cell & bellows type X
13. Level Switches—float type X
14. Orifice Plates X
15. Pressure Gauges X
16. Pressure Instruments—all types X
17. Pressure Regulators X
18. Pressure Switches X

NOTES:

(1) Caution—do not force reverse flow.