Inflection Point Engineering Section 11 — Refractory, Insulation & Fireproofing

Internal Insulation and Refractory Lining Inspection

IPE Engineering Practice IPE-EP-11-1-1C

Document number: IPE-EP-11-1-1C · Section: 11 — Refractory, Insulation & Fireproofing

Figure

THE MANUFACTURER OF EQUIPMENT PURCHASED BY INFLECTION POINT ENGINEERING, LLC SHALL BE RESPONSIBLE FOR MEETING ALL APPLICABLE REQUIREMENTS OF THE IPE ENGINEERING PRACTICES AND OTHER DOCUMENTS REFERENCED THEREIN REGARDLESS OF WHETHER THE ITEMS ARE INSPECTED BY A IPE REPRESENTATIVE.

REFERENCES

THE LATEST EDITION OF THE FOLLOWING STANDARDS AND PUBLICATIONS ARE REFERRED TO HEREIN.

IPE ENGINEERING PRACTICES

EP 11-1-1 INTERNAL INSULATING AND REFRACTORY LINING

ASTM SPECIFICATIONS

ASTM C133 COLD CRUSH STRENGTH AND MODULUS OF RUPTURE

ASTM C704-88 ABRASION RESISTANCE OF REFRACTORY MATERIALS AT ROOM TEMPERATURE ASTM C860 PRACTICES FOR DETERMINING CONSISTENCY IN REFRACTORY CONCRETES

STEEL STRUCTURES PAINTING COUNCIL

SSPC-SP6 COMMERCIAL BLAST CLEANING SSPC-SP10 NEAR WHITE BLAST CLEANING

FREQUENCY OF CONTACT BY THE INSPECTOR: (CHECK ONE)

LEVEL 1: ON CALL BY FABRICATOR LEVEL 2: ONCE EVERY TWO WEEKS LEVEL 3: EVERY WEEK

LEVEL 4: DAILY

LEVEL 5: RESIDENT LEVEL 6: OTHER, SPECIFY

LEVEL OF INSPECTION BY THE INSPECTOR: (CHECK ONE)

LEVEL 1: PREFABRICATION MEETING, DOCUMENT REVIEW, AND FINAL INSPECTION

LEVEL 2: PREFABRICATION MEETING, DOCUMENT REVIEW, REVIEW ITEMS, AND FINAL INSPECTION LEVEL 3: PREFABRICATION MEETING, DOCUMENT REVIEW, REVIEW ITEMS, WITNESS POINTS, AND FINAL

INSPECTION

LEVEL 4: PREFABRICATION MEETING, DOCUMENT REVIEW, REVIEW ITEMS, WITNESS POINTS, HOLD POINTS, AND FINAL INSPECTION

LEVEL 5: OTHER, SPECIFY

DOCUMENT REVIEW (SHOP INSPECTOR SHALL REVIEW):

DOCUMENT DESCRIPTION INSPECTOR'S INITIALS (REVIEW COMPLETE) DATE
IPE PURCHASE DOCUMENTS
DRAWINGS AND SPECIFICATIONS
DATA SHEETS (6.0)
CONTRACTOR SPECIFICATIONS (5.0)
QUALITY CONTROL PLAN
MATERIAL RECEIVING SIGN-OFF AND PMI
MATERIAL TEST REPORTS (19.1.5, 19.2, 19.3)
WELDING PROCEDURE SPECS.
WELDER QUALIFICATION RECORDS
WELDER TRACEABILITY DOCUMENT
FABRICATION PLAN/SHOP TRAVEL
IDENTIFICATION OF CRITICAL DIMENSONS
SUB-CONTRACTOR Q/C REPORTS
DRYOUT SCHEDULES AND THERMOCOUPLE PLACEMENT (18.0)
AUTHORIZED WAIVERS AND/OR DEVIATIONS REVIEW
REVIEW OF SUBORDERS OF UNPRICED PURCHASE ORDERS TO SUBVENDORS FOR COMPLIANCE WITH IPE ENGINEERING PRACTICES
EQUIPMENT ID JOB NO. DOCUMENT NO. REV.

GENERAL INSPECTION REQUIREMENTS

R CHECK: THE SHOP INSPECTOR SHALL REVIEW DOCUMENTED RESULTS OF INSPECTION PERFORMED BY VENDOR'S INSPFCTOR OR SUBCONTRACTED INSPECTOR.

W CHECK: INDICATES THE SHOP INSPECTOR SHALL WITNESS ITEMS DURING FABRICATION SHOP SHALL NOTIFY INSPECTOR 2 DAYS IN ADVANCE OF FABRICATION POINT BUT NEED NOT HOLD PRODUCTION FOR INSPECTION.

H CHECK: INDICATES THE SHOP INSPECTOR SHALL INSPECT ITEMS DURING HOLD ON FABRICATION. SHOP SHALL NOTIFY INSPECTOR FIVE DAYS IN ADVANCE OF FABRICATION POINT AND SHALL NOT CONTINUE AFFECTED PRODUCTION UNTIL INSPECTOR PERFORMS AND IMPROVES FABRICATION AFTER INDICATED INSPECTION.

R W H INSPECTION/TESTING ACTIVITY INSPECTOR’S INITIALS (REVIEW COMPLETE) DATE
MATERIAL QUALIFICATION MATERIAL QUALIFICATION MATERIAL QUALIFICATION MATERIAL QUALIFICATION MATERIAL QUALIFICATION MATERIAL QUALIFICATION
REFRACTORY PREQUALIFICATION (19.2)
ANCHORS (19.1.5) INCLUDING PMI CHECK
PRODUCTION
INSTALLATION QUALIFICATION INSTALLATION QUALIFICATION INSTALLATION QUALIFICATION INSTALLATION QUALIFICATION INSTALLATION QUALIFICATION INSTALLATION QUALIFICATION
GUNITE (19.4.2)
POURED/CAST (19.4.3)
THIN EROSION RESISTANT LININGS (19.4.4)
WELDING (13.1.3, 13.1.4, 13.2.1,13.2.2, 19.4.5)
SHIPPING/HANDLING/MARKING/STORAGE SHIPPING/HANDLING/MARKING/STORAGE SHIPPING/HANDLING/MARKING/STORAGE SHIPPING/HANDLING/MARKING/STORAGE SHIPPING/HANDLING/MARKING/STORAGE SHIPPING/HANDLING/MARKING/STORAGE
MATERIAL MARKING (14.3, 14.4, 15.1.2)
MATERIAL AGE (14.1, 14.2, 14.8)
PACKAGING (14.4, 14.5, 14.6, 14.7, 14.8)
TEMPERATURE (15.2.1.7, 15.3.1.1, 15.4.1)
HANDLING (15.1.1, 15.1.2, 15.4.15, 16.6)
EQUIPMENT ID JOB NO. DOCUMENT NO. REV.

GENERAL INSPECTION REQUIREMENTS

R CHECK: THE SHOP INSPECTOR SHALL REVIEW DOCUMENTED RESULTS OF INSPECTION PERFORMED BY VENDOR'S INSPFCTOR OR SUBCONTRACTED INSPECTOR.

W CHECK: INDICATES THE SHOP INSPECTOR SHALL WITNESS ITEMS DURING FABRICATION SHOP SHALL NOTIFY INSPECTOR 2 DAYS IN ADVANCE OF FABRICATION POINT BUT NEED NOT HOLD PRODUCTION FOR INSPECTION.

H CHECK: INDICATES THE SHOP INSPECTOR SHALL INSPECT ITEMS DURING HOLD ON FABRICATION. SHOP SHALL NOTIFY INSPECTOR FIVE DAYS IN ADVANCE OF FABRICATION POINT AND SHALL NOT CONTINUE AFFECTED PRODUCTION UNTIL INSPECTOR PERFORMS AND IMPROVES FABRICATION AFTER INDICATED INSPECTION.

R W H INSPECTION/TESTING ACTIVITY INSPECTOR’S INITIALS (REVIEW COMPLETE) DATE
SURFACE PREPARATION/CLEANLINESS SURFACE PREPARATION/CLEANLINESS SURFACE PREPARATION/CLEANLINESS SURFACE PREPARATION/CLEANLINESS SURFACE PREPARATION/CLEANLINESS SURFACE PREPARATION/CLEANLINESS
PRIOR TO WELDING (8.1.3, 8.1.4, 12.4.1, 12.5, 12.6, 12.7, 13.1.1)
PRIOR TO COATING (12.2, 12.3, 12.7, 12.8)
PRIOR TO REFRACTORY INSTALLATION (SEE DAILY LOG SHEET)
EQUIPMENT CLEANLINESS (SEE DAILYLOG SHEET)
DURING INSTALLATION (SEE DAILY LOG SHEET)
ANCHOR INSTALLATION ANCHOR INSTALLATION ANCHOR INSTALLATION ANCHOR INSTALLATION ANCHOR INSTALLATION ANCHOR INSTALLATION
MATERIAL (8.1.1, 8.3.1, 8.3.5, 8.6.2, 8.6.3, 19.1.5)
DESIGN (8.2.1, 8.2.3, 8.3.2, 8.3.3, 8.3.5, 8.4.1, 9.0)
SPACING (8.2.1, 8.2.4, 8.3.5, 8.4.2, 8.5.1, 8.5.2)
WELDING (8.7.1, 8.7.2, 19.4.5)
HEIGHT (8.1.3, 8.3.2, 8.4.3, 8.5.5)
ADDITIONAL DIMENSIONAL CHECKS (8.2.2, 8.5.1, 13.1.5, 13.2.3, 13.2.7, 13.2.8)
CURING AND DRYOUT (SEE SECTIONS 16.0 AND 18.0 FOR REQUIREMENTS) CURING AND DRYOUT (SEE SECTIONS 16.0 AND 18.0 FOR REQUIREMENTS) CURING AND DRYOUT (SEE SECTIONS 16.0 AND 18.0 FOR REQUIREMENTS) CURING AND DRYOUT (SEE SECTIONS 16.0 AND 18.0 FOR REQUIREMENTS) CURING AND DRYOUT (SEE SECTIONS 16.0 AND 18.0 FOR REQUIREMENTS) CURING AND DRYOUT (SEE SECTIONS 16.0 AND 18.0 FOR REQUIREMENTS)
CASING TEMPERATURE
CURING TIME
CURING COMPOUND APPLICATION (SEE DAILY LOG SHEETS)
DRYOUT

DAILY LOG SHEET

AS A MINIMUM, THE FOLLOWING LEVELS OF INSPECTION SHALL BE PERFORMED:

P CHECK: CHECK PRIOR TO STARTING WORK ON EACH SHIFT

R CHECK: IN ADDITION TO "P" CHECK, MAKE RANDOM CHECKS DURING SHIFT DATE: INSPECTOR’S NAME AND INITIALS:

READINGS READINGS
TIME VALUE
R CASING TEMPERATURES (15.2.1.4, 15.2.1.5,
15.3.1.4, 15.3.1.5, 15.4.6, 15.4.8, 16.2, 16.5, 16.7)
R WATER TEMPERATURE (15.1.3)
R WATER AMOUNT (15.2.1.1, 15.4.3, 15.4.4)
R AMBIENT TEMPERATURE (15.3.1.6, 15.4.8)
R MIX TEMPERATURE (15.2.1.2, 15.2.1.3, 15.4.5,
15.4.7)
R MIXING TIME (15.4.11, 15.4.13)
R LINING THICKNESS (15.1.12, 15.5.3)

DAILY LOG SHEET

AS A MINIMUM, THE FOLLOWING LEVELS OF INSPECTION SHALL BE PERFORMED:

P CHECK: CHECK PRIOR TO STARTING WORK ON EACH SHIFT

R CHECK: IN ADDITION TO "P" CHECK, MAKE RANDOM CHECKS DURING SHIFT DATE: INSPECTOR’S NAME AND INITIALS:

TIME INSPECTOR’S INITIALS
P WATER QUALITY (15.1.3, 15.1.4)
P FIBER ADDITIONS (11.0, 15.1.10, 15.1.11)
R CASTING DROP HEIGHT (15.2.2.5)
R APPLICATION POSITION (15.2.2.6, 15.2.3.1,
15.2.3.2, 15.4.15)
R GUNITE AREA (15.2.3d)
P ROTATING/MOVING OF PARTS (15.1.1, 15.4.15)
R CURING COMPOUND APPLICATION (15.2.1.14, 16.1, 16.4)
R VIBRATOR PLACEMENT
R FORMS (15.1.8, 15.3.1.3, 16.4)

DAILY LOG SHEET

AS A MINIMUM, THE FOLLOWING LEVELS OF INSPECTION SHALL BE PERFORMED:

P CHECK: CHECK PRIOR TO STARTING WORK ON EACH SHIFT

R CHECK: IN ADDITION TO "P" CHECK, MAKE RANDOM CHECKS DURING SHIFT DATE: INSPECTOR’S NAME AND INITIALS:

SURFACE PREPARATION/CLEANLINESS TIME INSPECTOR’S INITIALS
R PRIOR TO REFRACTORY INSTALLATION (12.0, 15.1.8, 15.1.13, 15.1.14)
R EQUIPMENT CLEANLINESS (15.1.6, 16.4.12,
15.4.16)
R DURING INSTALLATION (15.2.1.h, 15.2.1.k, 15.2.1.l, 15.2.1.m, 15.2.2.d, 15.2.3.c, 15.3.1.l,
15.3.2.j, 15.3.2.k, 15.3.2.l, 15.3.2.m, 15.5.4, 15.5.5)

PRODUCTION SAMPLES

SAMPLE DESIGNATION LOCATION TIME INSPECTOR'S INITIALS
INSPECTOR SIGN-OFF INSPECTOR SIGN-OFF INSPECTOR SIGN-OFF INSPECTOR SIGN-OFF
INITIALS NAME COMPANY SOCIAL SECURITY NUMBER
SUMMARY: