Inflection Point Engineering Section 8 — Heat Transfer Equipment

Air Cooled Heat Exchangers Inspection Checklist

IPE Engineering Practice IPE-EP-8-1-4C

Document number: IPE-EP-8-1-4C · Section: 8 — Heat Transfer Equipment

THE MANUFACTURER OF EQUIPMENT PURCHASED BY IPE COMPANY SHALL BE RESPONSIBLE FOR MEETING ALL APPLICABLE REQUIREMENTS OF THE IPE ENGINEERING PRACTICE AND OTHER DOCUMENTS REFERENCED THEREIN REGARDLESS OF WHETHER THE ITEMS ARE INSPECTED BY A IPE REPRESENTATIVE.

REFERENCES

THE LATEST EDITION OF THE FOLLOWING STANDARDS AND PUBLICATIONS ARE REFERRED TO HEREIN

IPE ENGINEERING PRACTICES

EP 7-1-5 WELDING REQUIREMENTS FOR PRESSURE VESSLES EP 8-1-4 AIR COOLED HEAT EXCHANGERS

EP 10-3-1 SHOP PAINTING

API

API 661 AIR COOLED HEAT EXCHANGERS FOR GENERAL PLANT SERVICE

FREQUENCY OF CONTACT BY THE INSPECTOR (CHECK ONE)

LEVEL L: ON CALL BY FABRICATOR LEVEL 2: ONCE EVERY TWO WEEKS LEVEL 3: EVERY WEEK

LEVEL 4: DAILY

LEVEL 5: RESIDENT

LEVEL 6. OTHER, SPECIFY

LEVEL OF INSPECTION BY THE INSPECTOR (CHECK ONE)

LEVEL L: PREFABRICATION MEETING, DOCUMENT REVIEW, AND FINAL INSPECTION

LEVEL 2: PREFABRICATION MEETING, DOCUMENT REVIEW. REVIEW ITEMS. AND FINAL INSPECTION L EVEL 3: PREFABRICATION MEETING. DOCUMENT REVIEW, REVIEW ITEMS. WITNESS POINTS, AND FINAL INSPECTION

LEVEL 4: PREFABRICATION MEETING, DOCUMENT REVIEW, REVIEW ITEMS, WITNESS POINTS, HOLD POINTS, AND FINAL INSPECTION

LEVEL 5. OTHER, SPECIFY

DOCUMENT REVIEW (SHOP INSPECTOR SHALL REVIEW)

DOCUMENT DESCRIPTION
(REFERENCES TO EP 8-1-4 UNLESS OTHERWISE NOTED)
INSPECTOR’S INITIALS (REVIEW COMPLETE) DATE
IPE PURCHASE DOCUMENTS
DRAWINGS AND SPECIFICATIONS
MANUFACTURERS FINAL RECORDS (3.2.1)
QUALITY CONTROL MANUAL
MANUFACTURER’S DATA REPORT (3.2.3)
NON ANSI B16.5 FORGING MATERIAL PROPERTIES
QUALITY CONTROL PLAN
MATERIAL RECEIVING SIGN-OFF
IMPACT TEST REPORTS
MATERIAL TEST REPORTS
TEST EQUIPMENT CALIBRATION CERTIFICATIONS
WELDING PROCEDURE SPECS (API 661:6.1.1.2)
WELDER QUALIFICATION RECORDS (API 661:6.1.1.2)
WELDER TRACEABILITY DOCUMENT
NDE PROCEDURES
NDE TEST REPORTS
NDE PERSONNEL CERTIFICATION
FABRICATION PLAN/SHOP TRAVELER
IDENTIFICATION OF CRITICAL DIMENSIONS
DAILY COATING INSPECTION REPORT (EP 10-3-1:10.8)
SUB-CONTRACTOR Q/C REPORTS
NAME PLATE RUBBINGS (7.5)
AUTHORIZED WAIVERS AND/OR DEVIATIONS REVIEW
REVIEW OF SUBORDERS OF UNPRICED PURCHASE ORDERS TO SUB- VENDORS FOR COMPLIANCE WITH IPE ENGINEERING PRACTICE

GENERAL FABRICATION INSPECTION REQUIREMENTS (ALL FABRICATED EQUIPMENT)

R CHECK: THE SHOP INSPECTOR SHALL REVIEW DOCUMENTED RESULTS OF INSPECTION PERFORMED BY VENDOR'S INSPFCTOR OR SUBCONTRACTED INSPECTOR.

W CHECK: INDICATES THE SHOP INSPECTOR SHALL WITNESS ITEMS DURING FABRICATION SHOP SHALL NOTIFY INSPECTOR 2 DAYS IN ADVANCE OF FABRICATION POINT BUT NEED NOT HOLD PRODUCTION FOR INSPECTION.

H CHECK: INDICATES THE SHOP INSPECTOR SHALL INSPECT ITEMS DURING HOLD ON FABRICATION. SHOP SHALL NOTIFY INSPECTOR FIVE DAYS IN ADVANCE OF FABRICATION POINT AND SHALL NOT CONTINUE AFFECTED PRODUCTION UNTIL INSPECTOR PERFORMS AND IMPROVES FABRICATION AFTER INDICATED INSPECTION.

R W H INSPECTION/TESTING ACTIVITY (REFERENCES TO EP 8-1-4 UNLESS OTHERWISE NOTED) INSPECTOR’S INITIALS (REVIEW COMPLETE) DATE
FIT-UPS WELD ROOTS/WELD BEVELS
GENERAL FABRICATION CHECKS (API 661:7.2)
GENERAL WELDING FABRICATION CHECKS (API 661:7.2)
PWHT PREPARATIONS (EP 7-1-5)
REVIEW OF COLD WORKED PARTS PWHT REQUIREMENTS (6.2.8)
NAMEPLATE REQUIREMENTS (7.5)
TUBE HOLE DIAMETERS AND
TOLERANCES (API 661: 6.3.1 AND AS AMENDED BY EP 8-1-4)
EXPANSION OF TUBES INTO TUBE HOLES (6.3.3)
TUBE HOLE GROOVE DIMENSIONS (API 661: 6.3.2)
ALIGNMENT AND TOLERANCE CHECKS (API 661: 6.6)
CLEANLINESS CHECK PRIOR TO FINAL INSPECTION (7.1)
PMI OF ALL APPLICABLE MATERIALS (7.1.7)
RT LOCATION SELECTION (API 661: 7.2.2 – 7.2.6 AND AS MODIFIED IN EP 8-1-4)
RT OF WELDS IN COLD WORKED PARTS
MT/PT OF ROOT AND FINAL WELDS (API 661: 7.2.7-12)
NDE OF REPAIRS
WELD HARDNESS CHECKS (API 661: 7.2.14)
PRESSURE TESTING (7.3)
MOTOR REQUIREMENTS (4.2.7)
SHOP RUN-IN AND VIBRATION MONITORING (7.4)
PREPARATION FOR SHIPMENT (API 661: 8.0)

GENERAL FABRICATION INSPECTION REQUIREMENTS (ALL FABRICATED EQUIPMENT)

R W H INSPECTION/TESTING ACTIVITY INSPECTOR’S INITIALS (REVIEW COMPLETE) DATE
WELDING INSPECTION (SEE EP 7-1-5) WELDING INSPECTION (SEE EP 7-1-5) WELDING INSPECTION (SEE EP 7-1-5) WELDING INSPECTION (SEE EP 7-1-5) WELDING INSPECTION (SEE EP 7-1-5) WELDING INSPECTION (SEE EP 7-1-5)
WELDING PROCESS REQUIREMENTS (6.2,3,4,5,6)
WELDER PERFORMANCE QUALIFICATION TESTS (7.0)
WELD JOINT DESIGN (8.0)
PREHEAT AND INTERPASS REQUIREMENTS (9.1)
FILLER METAL REQUIREMENTS (9.2)
WELDING TECHNIQUE REQUIREMENTS (9.3)
WELDER IDENTIFICATION (9.4)
PWHT REQUIREMENTS(10.0)
TUBE WELDS 2 PASS WITH THROAT THICKNESS EQUAL TO TUBE THICKNESS
EXTERIOR COATING INSPECTION WHEN REQUIRED (SEE EP 10-3-1) EXTERIOR COATING INSPECTION WHEN REQUIRED (SEE EP 10-3-1) EXTERIOR COATING INSPECTION WHEN REQUIRED (SEE EP 10-3-1) EXTERIOR COATING INSPECTION WHEN REQUIRED (SEE EP 10-3-1) EXTERIOR COATING INSPECTION WHEN REQUIRED (SEE EP 10-3-1) EXTERIOR COATING INSPECTION WHEN REQUIRED (SEE EP 10-3-1)
SAND BLASTED SURFACES (10.5)
COATINGS PREPARATION (10.6)
WET FILM THICKNESS MEASUREMENTS (10.13)
DRY FILM THICKNESS MEASUREMENTS (10.11)
HOLIDAY TESTING OF COATING (10.15)
INSPECTOR SIGN-OFF INSPECTOR SIGN-OFF INSPECTOR SIGN-OFF INSPECTOR SIGN-OFF
INITIALS NAME COMPANY SOCIAL SECURITY NUMBER
SUMMARY: