Inflection Point Engineering Section 6 — Rotating Equipment

Special Purpose Lube/Seal Oil Systems

IPE Engineering Practice IPE-EP-6-9-1

Document number: IPE-EP-6-9-1 · Section: 6 — Rotating Equipment

The following paragraph numbers refer to API 614, Third Edition, August 1992, which is part of this Engineering Practice.

INTRODUCTION

requirements for lubrication, shaft-sealing, and control-oil systems correspond to those of APl Standard 614, Third Edition, August 1992, with the specific options, deletions, additions, or modifications sanctioned in this Practice.

The paragraph numbers in this specification correspond to those used on APl 614. Paragraph numbers may not be consecutive and all APl 614 paragraphs not mentioned herein shall be considered to be verbatim requirements of this specification.

Instructions contained in this specification such as "add" or "substitute" shall be interpreted as follows: if information is "added" to an existing paragraph in the APl Standard, the requirements of this specification shall be read as a continuation of that particular APl paragraph. If information is "substituted", the affected APl requirement shall be replaced in its entirety by the requirements of this specification. If (New) is next to a paragraph number, not appearing in APl 614, it shall be read as an added requirement.

The Purchaser's requirements for all paragraphs in APl 614 which require a Purchaser's decision (bulleted paragraphs) are indicated on the data sheets or in this specification. If not addressed in the inquiry, the proposal shall clearly state the basis included in the pricing furnished.

NOTE: U.S. Customary units shall be regarded as standard. SI (metric) units in APl 614 and this supplement are included for convenience reference only and shall not be interpreted as precise conversions.

Table 1 records the vendor drawing and data requirements.

GENERAL

1.1.1 (Substitute) This Practice, together with the requisition, data sheets, and all attachments thereto, are the minimum requirements for oil systems.

1.2.1 (Add) Metric fasteners and flanges constitute alternative design features and must be cited as exceptions in the vendor proposal.

Purchase Order Data Sheets

Project Specification(s) Referenced Industry Standards

STANDARDS AND PUBLICATIONS

Engineering Practices
EP 1-1-3 Deviations to Engineering Practices EP 6-3-1 General Purpose Steam Turbines
EP 6-7-1 Special Requirements for Rotating Equipment
EP 6-8-1 Field Storage and Installation of Rotating Equipment EP 12-1-1 Control Systems
EP 12-2-1 Control Systems Installations
EP 13-3-1 Induction Motors 500 HP and Below

BASIC DESIGN

2.1.10 (Add) Piping, filters, and reservoirs shall be grounded to prevent static electrical charge build up as necessary.

2.1.16 (Add) Crossover piping and valves shall be furnished between dual equipment items, such as filters and coolers, to permit filling idle equipment from the active equipment. In addition, valved drain connections and all necessary piping shall be furnished for all equipment. As a minimum, valved vent and drain connections shall be provided for oil filters and for oil coolers (including the water side of coolers).

2.1.18 (Revise) Omit the bullet and the phrase "if specified by the purchaser".

2.1.20 (Add) The vendor shall furnish a rundown tank properly designed to provide a fully lubricated coast-down of the equipment train upon loss of pressurized lubrication. Continuous oil through-flow is required so as to avoid the oil being in the stagnant (quiescent) state for extended periods prior to "running down" during an emergency event.

2.1.24 (New) The unit shall be designed and constructed to provide adequate clearance for maintenance and operational concerns, e.g., clearance to turn valves, read gauges, service filters, remove bundles. In addition, pumps and drivers shall be removable while the unit is in service.

2.2 Baseplates

2.2.4 (Substitute) All walk and work areas shall have a non-skid surface. In areas that are expected to be continually oily or wet, hot dipped galvanized steel grating or expanded metal mesh shall be securely attached to provide safe footing for personnel (Checker or diamond plate is not acceptable as "non-skid"). Walk and working areas shall be free of tripping hazards. Where walking surfaces are located, boltheads shall be counter-sunk.

2.3 Oil Reservoirs

2.3.1 (Add) Pumps, coolers, filters, etc. shall not be mounted on top of the reservoir.

2.3.5.c (Add) The gauge shall be valved and flanged to allow for removal and maintenance during operation.

2.4 Pumps and Drivers

2.4.1 (Purchaser's Decision) The pumps shall be horizontal.

2.4.10 (Add) If parallel pressure regulators and/or pressure relief valves are supplied for the discharge lines of positive displacement pumps, the valves shall be located upstream of the discharge check valve.

2.5 Coolers

2.5.1 (Add) Coolers shall be upstream of filters.

2.5.3 (Revise) The minimum tube wall thickness shall be 16 BWG.

2.5.9 (New) A sampling point shall be provided immediately downstream of the bearing housings and the filters to allow representative samples of the circulating oil to be obtained.

2.6.5 (Add) A local differential pressure indicator shall be installed to measure filter differential pressure.

2.13 Piping

2.13.1 (Add) The system arrangement and orientation/location of the Purchaser's connections shall be mutually agreed upon prior to system fabrication.

2.13.3  (Add) A minimum of five (5) percent radiography of piping welds in pressurized oil piping shall be conducted, including a minimum of one weld in each service at locations subject to Purchaser's approval.

2.13.5.f (New) Provisions for adequate clearance for the addition of insulation where required.

2.13.7 (Purchaser's Option) In seal oil systems, double block valves shall be provided for all vents and drains used in hydrogen or toxic service.

2.13.9 (Add) All instrument interconnecting tubing shall be 1/2 inch OD (0.065 inch minimum wall thickness) annealed, Type 316 seamless stainless steel per ASTM A269. Tubing fittings shall be of Type 316 stainless steel, Swagelok manufactured.

2.13.9.3 (Purchaser's Option) All 3/4 inch and 1 inch tubing fittings shall be 316 stainless steel, Crawford Swagelok type.

2.13.10.3 (Purchaser's Option) Carbon steel slip-on flanges are not allowed. Stainless steel weld neck flanges shall be used. Van stone or lap joint flanges are not acceptable.

2.13.11.4 (Add) Dead end stubs on lube oil pipe downstream of the filters are not permitted.

2.13.12  (Add) Provisions for ferrographic sampling shall be made if specified on the data sheets by the Purchaser.

INSTRUMENTATION, CONTROL AND ELECTRICAL SYSTEMS

3.1.2 (Add) All instruments shall be permanently tagged with item number and service. Instrumentation and installation shall comply with EP 12-1-1 and EP 12-2-1.

3.1.5 (Add) Piping, tubing and conduits shall be arranged to provide adequate clearance for the addition of insulation.

3.3 Alarms and Shutdowns

3.3.1 (Add) Shutdowns shall only initiate from the concurrent action of at least 2 of 3 sensors (i.e. voting-logic).

3.3.5 Shutdown switches shall open (de-energize) to trip.

3.4 Instrumentation

3.4.1 Thermometers

3.4.1.1 (Purchaser's Decision) Dial thermometers shall be bimetallic with a 5 inch adjustable angle dial face and stainless steel case. Thermowells shall have 1 inch male NPT threads. Wells on insulated lines and vessels shall have a 2-1/2 inch extension neck.

All pressure gauges shall be 4-1/2 inch in diameter with 1/2 inch NPT connections. All receiver gauges shall be 6 inches in diameter with 1/4 inch connections. Accuracy of all process gauges shall be guaranteed at a minimum of 1/2 of 1% of maximum scale reading over the entire scale. Dials shall be white with black figures.

INSPECTION AND TESTING

4.1.3 (Add) "Sufficient advance notification" shall be five working days in writing.

4.2.1.5  (New) Prior to hydrostatic and operational tests, coupling alignment, piping strain and equipment soft foot shall be checked (on oil pumps) in accordance with the requirements specified in EP 6-8-1. The inspection shall be witnessed by the Purchaser's inspector. The vendor shall make the necessary corrections to meet the allowable limits specified in EP 6-8- 1.

4.4 Preparation for Shipment
4.4.1 (Add) The oil system shall be prepared for shipment in accordance with EP 6-7-1. The system shall be suitable for outdoor storage at the job site for at least six months or a mutually agreed period.
5.0 VENDOR'S DATA
5.2 Contract Data
5.2.3 Drawings
5.2.3.1 (Add) The Owner's name and item (tag) number shall be included on the drawings.
5.2.3.7 (Revise) Omit both occurrences of the phrase "if specified by the purchaser."
5.2.4 Data
5.2.4.2.e (Revise) Omit the bullet and the phrase "when specified by the Purchaser."
5.2.4.2.f (New) Calibration certificates for all instruments used during testing of the system.
5.2.5 Progress Reports

Omit the bullet and the words "when specified".

6.0 TABLES

TABLE 1 DOCUMENTATION REQUIREMENTS FOR SPECIAL PURPOSE LUBE/SEAL OIL SYSTEMS PER EP 6-9-1

Item Description Format (1) As-Built
1 Certified dimensional outline drawing and list of connections See EP 2-5-2 Yes
2 Cross-sectional drawings and bill of materials See EP 2-5-2 Yes
3 Seal-oil schematic and bill of materials, including component sizing criteria See EP 2-5-2 Yes
4 Seal-oil arrangement drawing and list of connections See EP 2-5-2 Yes
5 Seal-oil component drawings and data See EP 2-5-2 Yes
6 Lube-oil schematic and bill of materials, including component sizing criteria See EP 2-5-2 Yes
7 Lube-oil arrangement drawing and list of connections See EP 2-5-2 Yes
8 Lube-oil component drawings and data See EP 2-5-2 Yes
9 Electrical and instrumentation schematics and bill of materials See EP 2-5-2 Yes
10 Electrical and instrumentation arrangement drawing and list of connections See EP 2-5-2 Yes
11 Console test agenda See EP 2-5-2 Yes
12 Weld procedures See EP 2-5-2 Yes
13 Hydrostatic test logs See EP 2-5-2 Yes
14 Operational test logs See EP 2-5-2 Yes
15 As-built data sheets See EP 2-5-2 Yes
16 Operating and maintenance manuals See EP 2-5-2 Yes
17 Spare parts recommendation and price list See EP 2-5-2 Yes

NOTE:

(1) If the document cannot be provided in the format as indicated, the Manufacturer shall consult with the Owner's Engineer for an acceptable alternative.