Section 6 — Rotating Equipment
IPE Engineering Practice IPE-EP-6-3-2C
Document number: IPE-EP-6-3-2C · Section: 6 — Rotating Equipment
THE MANUFACTURER OF EQUIPMENT PURCHASED BY EAGLE POINT REFINERY REFINING COMPANY SHALL BE RESPONSIBLE FOR MEETING ALL APPLICABLE REQUIREMENTS OF THE EAGLE POINT REFINERY ENGINEERING PRACTICES AND OTHER DOCUMENTS REFERENCED THEREIN REGARDLESS OF WHETHER THE ITEMS ARE INSPECTED BY A EAGLE POINT REFINERY REPRESENTATIVE.
THE LATEST EDITION OF THE FOLLOWING STANDARDS AND PUBLICATIONS ARE REFERRED TO HEREIN.
EP 6-3-2 SPECIAL PURPOSE STEAM TURBINES EP 10-2-3 MATERIAL HARDNESS REQUIREMENTS
LEVEL 1: ON CALL BY FABRICATOR LEVEL 2: ONCE EVERY TWO WEEKS LEVEL 3: EVERY WEEK
LEVEL 2: PREFABRICATION MEETING, DOCUMENT REVIEW, REVIEW ITEMS, AND FINAL INSPECTION LEVEL 3: PREFABRICATION MEETING, DOCUMENT REVIEW, REVIEW ITEMS, WITNESS POINTS, AND FINAL INSPECTION
LEVEL 4: PREFABRICATION MEETING, DOCUMENT REVIEW, REVIEW ITEMS, WITNESS POINTS, HOLD POINTS, AND FINAL INSPECTION
| EQUIPMENT ID | JOB NO. | DOCUMENT NO. | REV. |
|---|
| DOCUMENT DESCRIPTION | INSPECTOR'S INITIALS (REVIEW COMPLETE) |
DATE | |
|---|---|---|---|
| PREFABRICATION MEETING | PREFABRICATION MEETING | PREFABRICATION MEETING | PREFABRICATION MEETING |
| 1. | EAGLE POINT REFINERY PURCHASE DOCUMENTS | ||
| 2. | SPECIFICATIONS, APPROVED DRAWINGS, PARTS LISTS AND ASSEMBLY PROCEDURES (EP 6-3-2, 5.2.3.4, 5.2.3.5, 5.2.5.5) | ||
| 3. | VENDOR QUALITY CONTROL MANUAL | ||
| 4. | VENDOR QUALITY CONTROL PLAN | ||
| 5. | IDENTIFICATION OF CRITICAL DIMENSIONS (APPENDIX E. PARAGRAPH #41) | ||
| 6. | SUB-CONTRACTOR Q/C REPORTS | ||
| 7. | AUTHORIZED WAIVERS AND/OR DEVIATIONS REVIEW | ||
| 8. | CUSTOMER INSPECTION SCHEDULE (4.1.4.1) | ||
| 9. | REVIEW OF SUBORDERS OF UNPRICED PURCHASE ORDERS TO SUBVENDORS FOR COMPLIANCE WITH EAGLE POINT REFINERY ENGINEERING PRACTICES | ||
| 10. | WELDING PROCEDURES SPECS - PIPE (2.11.3.1, 3.6.1.1, AND 2.11.3.6. 3) - STEEL CASINGS AND PLATE (2.11.3.1 AND .3) |
||
| 11. | REPAIR PROCEDURES (2.11.2.3, 2.11.3.2) | ||
| FABRICATION DOCUMENTATION REVIEW | FABRICATION DOCUMENTATION REVIEW | FABRICATION DOCUMENTATION REVIEW | FABRICATION DOCUMENTATION REVIEW |
| 12. | MATERIAL REQUISITIONS (2.11.1.1 & .2) | ||
| 13. | MATERIAL RECEIVING SIGN-OFF | ||
| 14. | NDE PROCEDURES (4.2.2) | ||
| 15. | NDE PERSONNEL CERTIFICATION | ||
| 16. | IMPACT TEST REPORTS ( 2.11.1.15 AND 16 ) | ||
| 17. | MATERIAL TEST REPORTS (5.2.5.2.a) | ||
| 18. | MATERIAL HARDNESS TEST REPORTS (5.2.5.2.) | ||
| 19. | WELDER TRACEABILITY DOCUMENTATION | ||
| 20. | MANUFACTURING PLAN/SHOP TRAVELER | ||
| 21. | PRESSURE CASING | ||
| 22. | FIT-UPS OF WELD ROOTS AND BEVELS | ||
| 23. | UT OF WELDS (4.2.2.1.2) | ||
| 24. | RT OF WELDS - PRESSURE CASING (4.2.2.1.1) | ||
| 25. | - PIPING, STEAM (3.5.1.1) | ||
| 26. | - PIPING, OIL (3.5.1.1) | ||
| 27. | MPI RESULTS (4.2.2.3) | ||
| 28. | MPI/UT OF NON-RADIOGRAPHABLE CASING CONNECTIONS | ||
| 29. | UT OF COMPLETED CASING CONNECTIONS | ||
| 30. | POST WELD HEAT TREAT (PWHT) PROCEDURES/REQUIREMENTS REVIEW AND APPROVAL (2.11.3.5.4 AND 2.11.3.6.4) | ||
| 31. | PWHT PREPARATIONS | ||
| 32. | AFTER PWHT | ||
| 33. | -MPI | ||
| 34. | -WELDING HEAT AFFECTED ZONE (HAZ) HARDNESS CHECK (2.11.3.) | ||
| 35. | -UT | ||
| 36. | -RADIOGRAPH | ||
| 37. | HYDROSTATIC TEST -CASINGS (4.3.2) | ||
| 38. | -PIPING (4.3.2) | ||
| 39. | |||
| 40. | |||
| 41. |
| EQUIPMENT ID | JOB NO. | DOCUMENT NO. | REV. |
|---|
R CHECK: THE SHOP INSPECTOR SHALL REVIEW DOCUMENTED RESULTS OF INSPECTION PERFORMED BY VENDOR'S INSPECTOR OR SUBCONTRACTED INSPECTOR.
W CHECK: INDICATES THE SHOP INSPECTOR SHALL WITNESS ITEMS DURING FABRICATION SHOP SHALL NOTIFY INSPECTOR 2 DAYS IN ADVANCE OF FABRICATION POINT BUT NEED NOT HOLD PRODUCTION FOR INSPECTION.
H CHECK: INDICATES THE SHOP INSPECTOR SHALL INSPECT ITEMS DURING HOLD ON FABRICATION. SHOP SHALL NOTIFY INSPECTOR FIVE DAYS IN ADVANCE OF FABRICATION POINT AND SHALL NOT CONTINUE AFFECTED PRODUCTION UNTIL INSPECTOR PERFORMS AND IMPROVES FABRICATION AFTER INDICATED INSPECTION.
| R | W | H | INSPECTION/TESTING ACTIVITY | INSPECTOR'S INITIALS (REVIEW COMPLETE) | DATE | |
|---|---|---|---|---|---|---|
| MACHINING INSPECTION | MACHINING INSPECTION | MACHINING INSPECTION | MACHINING INSPECTION | MACHINING INSPECTION | MACHINING INSPECTION | MACHINING INSPECTION |
| 1. | DIMENSIONAL CHECKS (INCLUDING ID AND OD SNAPS, LENGTHS AND FACE PARALLELISM, SEE DRAWINGS APP. E, Par. 2 AND 3) | |||||
| 2. | PRESSURE CASING | |||||
| 3. | SHAFT (INCLUDING RADIAL RUNOUTS) (APP. E. PAR. 41.a) | |||||
| 4. | DISC(S) (APP. E. PAR. 41.d AND e) | |||||
| 5. | BEARINGS (APP. E, PAR. 41.d AND e) | |||||
| 6. | ||||||
| 7. | ||||||
| 8. | ||||||
| PRIOR TO AND DURING ASSEMBLY | PRIOR TO AND DURING ASSEMBLY | PRIOR TO AND DURING ASSEMBLY | PRIOR TO AND DURING ASSEMBLY | PRIOR TO AND DURING ASSEMBLY | PRIOR TO AND DURING ASSEMBLY | PRIOR TO AND DURING ASSEMBLY |
| 9. | ASSEMBLED ROTOR RADIAL AND AXIAL RUNOUTS | |||||
| 10. | FINAL ROTOR RESIDUAL UNBALANCE AMPLITUDE AND PHASE ANGLES | |||||
| 11. | BEARING RADIAL CLEARANCES (5.2.4.2.k) | |||||
| 12. | ROTOR AXIAL CLEARANCES (5.2.4.2.k) | |||||
| 13. | THRUST DISC AXIAL RUNOUT (5.2.4.2.k) | |||||
| 14. | ROTOR END FLOAT (WITH THRUST DISC INSTALLED) (5.2.4.2.k) | |||||
| 15. | SHAFT SEAL CLEARANCES (5.2.4.2.k) | |||||
| 16. | VERIFY BEARING ATTACHMENT BOLT TORQUES (VENDOR SPECS) | |||||
| 17. | CASING SPLIT LINE BOLT TORQUES (VENDOR SPECS) | |||||
| 18. | VERIFY INLET AND OUTLET PIPE FLANGE INTERFACE LOCATIONS (APP. E. PAR.1a) | |||||
| 19. | VERIFY ALL PARTS ARE INSTALLED PER PARTS LIST (5.2.4.3b) | |||||
| 20. | COUPLING HUB BLUING CHECK | |||||
| 21. | ||||||
| 22. | ||||||
| 23. |
| EQUIPMENT ID | JOB NO. | DOCUMENT NO. | REV. |
|---|
R CHECK: THE SHOP INSPECTOR SHALL REVIEW DOCUMENTED RESULTS OF INSPECTION PERFORMED BY VENDOR'S INSPFCTOR OR SUBCONTRACTED INSPECTOR.
W CHECK: INDICATES THE SHOP INSPECTOR SHALL WITNESS ITEMS DURING FABRICATION SHOP SHALL NOTIFY INSPECTOR 2 DAYS IN ADVANCE OF FABRICATION POINT BUT NEED NOT HOLD PRODUCTION FOR INSPECTION.
H CHECK: INDICATES THE SHOP INSPECTOR SHALL INSPECT ITEMS DURING HOLD ON FABRICATION. SHOP SHALL NOTIFY INSPECTOR FIVE DAYS IN ADVANCE OF FABRICATION POINT AND SHALL NOT CONTINUE AFFECTED PRODUCTION UNTIL INSPECTOR PERFORMS AND IMPROVES FABRICATION AFTER INDICATED INSPECTION.
| R | W | H | INSPECTION/TESTING ACTIVITY | INSPECTION/TESTING ACTIVITY | INSPECTOR'S INITIALS (REVIEW COMPLETE) | DATE | |
|---|---|---|---|---|---|---|---|
| FUNCTIONAL CHECKS | FUNCTIONAL CHECKS | FUNCTIONAL CHECKS | FUNCTIONAL CHECKS | FUNCTIONAL CHECKS | FUNCTIONAL CHECKS | FUNCTIONAL CHECKS | FUNCTIONAL CHECKS |
| 1. | VERIFY OIL FLOW IS EVIDENT IN EACH DRAIN LINE SIGHT FLOW INDICATOR | VERIFY OIL FLOW IS EVIDENT IN EACH DRAIN LINE SIGHT FLOW INDICATOR | |||||
| 2. | ROTOR OVERSPEED TRIP (DO 3 TIMES) (4.3.3.3.5) | ROTOR OVERSPEED TRIP (DO 3 TIMES) (4.3.3.3.5) | |||||
| 3. | GOVERNOR SPEED CONTROL STABILITY AND RANGE (4.3.3.2.4) | GOVERNOR SPEED CONTROL STABILITY AND RANGE (4.3.3.2.4) | |||||
| 4. | HORIZONTAL (VERTICAL) SPLIT LINE LEAK TEST (4.3.3.3.1) | HORIZONTAL (VERTICAL) SPLIT LINE LEAK TEST (4.3.3.3.1) | |||||
| 5. | MECHANICAL RUNNING TEST (COMPLETE UNIT) (4.3.3) | MECHANICAL RUNNING TEST (COMPLETE UNIT) (4.3.3) | |||||
| 6. | PERFORMANCE TEST (COMPLETE UNIT, WHEN SPECIFIED) (4.3.4.1) | PERFORMANCE TEST (COMPLETE UNIT, WHEN SPECIFIED) (4.3.4.1) | |||||
| 7. | MECHANICAL TEST OF THE SPARE ROTOR ASSEMBLY (4.3.3.4.3) | MECHANICAL TEST OF THE SPARE ROTOR ASSEMBLY (4.3.3.4.3) | |||||
| 8. | SENTINEL VALVE (2.3.2) | SENTINEL VALVE (2.3.2) | |||||
| 9. | |||||||
| 10. | |||||||
| 11. | |||||||
| PREP TO SHIP - INSPECTION | PREP TO SHIP - INSPECTION | PREP TO SHIP - INSPECTION | PREP TO SHIP - INSPECTION | PREP TO SHIP - INSPECTION | PREP TO SHIP - INSPECTION | PREP TO SHIP - INSPECTION | PREP TO SHIP - INSPECTION |
| 12. | INSPECT BEARINGS (4.3.3.4.1) | INSPECT BEARINGS (4.3.3.4.1) | |||||
| 13. | INSPECT SHAFT SEALS | INSPECT SHAFT SEALS | |||||
| 14. | FLUSH PRESSURE CASING, SUPPLY AND DISCHARGE SECTIONS AND APPLY PRESERVATIVE (4.4.3.3) | FLUSH PRESSURE CASING, SUPPLY AND DISCHARGE SECTIONS AND APPLY PRESERVATIVE (4.4.3.3) | |||||
| 15. | FLUSH BEARING HOUSINGS AND APPLY PRESERVATIVE (4.4.3.4) | FLUSH BEARING HOUSINGS AND APPLY PRESERVATIVE (4.4.3.4) | |||||
| 16. | DRY OUT COOLING WATER PASSAGES AND APPLY PRESERVATIVE | DRY OUT COOLING WATER PASSAGES AND APPLY PRESERVATIVE | |||||
| 17. | MATCH MARK ALL MATING FLANGES | MATCH MARK ALL MATING FLANGES | |||||
| 18. | PAINT EXTERIOR NON-MACHINED SURFACES (4.4.3.1) | PAINT EXTERIOR NON-MACHINED SURFACES (4.4.3.1) | |||||
| 19. | COVER ALL OPENINGS WITH METAL CLOSURES (4.4.3.5) | COVER ALL OPENINGS WITH METAL CLOSURES (4.4.3.5) | |||||
| 20. | APPLY RUST PREVENTIVE TO EXTERIOR MACHINED PARTS (4.4.3.2) | APPLY RUST PREVENTIVE TO EXTERIOR MACHINED PARTS (4.4.3.2) | |||||
| 21. | VERIFY PROPER BRACING TO AVOID DAMAGE DURING SHIPPING (4.4.1) | VERIFY PROPER BRACING TO AVOID DAMAGE DURING SHIPPING (4.4.1) | |||||
| 22. | |||||||
| 23. | |||||||
| 24. | |||||||
| 25. |
| EQUIPMENT ID | JOB NO. | DOCUMENT NO. | REV. |
|---|
R CHECK: THE SHOP INSPECTOR SHALL REVIEW DOCUMENTED RESULTS OF INSPECTION PERFORMED BY VENDOR'S INSPFCTOR OR SUBCONTRACTED INSPECTOR.
W CHECK: INDICATES THE SHOP INSPECTOR SHALL WITNESS ITEMS DURING FABRICATION SHOP SHALL NOTIFY INSPECTOR 2 DAYS IN ADVANCE OF FABRICATION POINT BUT NEED NOT HOLD PRODUCTION FOR INSPECTION.
H CHECK: INDICATES THE SHOP INSPECTOR SHALL INSPECT ITEMS DURING HOLD ON FABRICATION. SHOP SHALL NOTIFY INSPECTOR FIVE DAYS IN ADVANCE OF FABRICATION POINT AND SHALL NOT CONTINUE AFFECTED PRODUCTION UNTIL INSPECTOR PERFORMS AND IMPROVES FABRICATION AFTER INDICATED INSPECTION.
| PREP TO SHIP -DOCUMENTATION REVIEW | PREP TO SHIP -DOCUMENTATION REVIEW | PREP TO SHIP -DOCUMENTATION REVIEW | PREP TO SHIP -DOCUMENTATION REVIEW | PREP TO SHIP -DOCUMENTATION REVIEW | PREP TO SHIP -DOCUMENTATION REVIEW | PREP TO SHIP -DOCUMENTATION REVIEW |
|---|---|---|---|---|---|---|
| 1. | INSTRUCTION MANUAL INCLUDED WITH TURBINE | |||||
| 2. | PRESSURE RELIEF VALVE(S) CERTIFICATION | |||||
| 3. | HYDROTEST CERTIFICATIONS | |||||
| 4. | FINAL MECHANICAL INSPECTION RECORDS | |||||
| 5. | TEST PERFORMANCE CURVES | |||||
| 6. | AS-BUILT DATA SHEETS | |||||
| 7. | SPECIAL TOOL LIST (3.6) | |||||
| 8. | PRESERVATION, PACKING AND SHIPPING PROCEDURES | |||||
| 9. | COMPLETE SPARE PARTS LIST | |||||
| 10. | PICTORIAL RECORD SHOWING SHOP ASSEMBLY AND DISASSEMBLY SEQUENCES WITH 100 TO 200 PHOTOS EACH. THE PICTORIAL RECORD SHALL: IDENTIFY CREW SIZE (I.E. MANPOWER REQUIREMENT) SEQUENTIALLY TRACK THE TIME IT TAKES FOR EACH STEP TO BE COMPLETED TRACK TOTAL ELAPSED TIME SINCE COMMENCEMENT OF ASSEMBLY/DISASSEMBLY |
|||||
| 11. | ||||||
| 12. |
| EQUIPMENT ID | JOB NO. | DOCUMENT NO. | REV. |
|---|
| SUMMARY: |
|---|
© 2026 Inflection Point Engineering, LLC. All rights reserved. The content of this page — including calculation methods, reference data, written analysis, interactive tools, and source code — is the intellectual property of Inflection Point Engineering, LLC and is protected under applicable copyright, trademark, and trade secret laws. Unauthorized reproduction, redistribution, modification, or derivative use in whole or in part is prohibited without prior written consent.
Disclaimer. This material is provided for informational and educational purposes only and does not constitute professional engineering advice. Calculations, reference data, and methodologies are based on published standards and accepted engineering practice but are not a substitute for engineering judgment, site-specific analysis, or review by a licensed Professional Engineer. Inflection Point Engineering, LLC makes no warranties, express or implied, regarding the accuracy, completeness, or fitness for a particular purpose of any content presented here, and shall not be liable for any direct, indirect, incidental, or consequential damages arising from its use. Users assume all risk associated with applying this content to real-world design, operations, or decisions.
© 2026 Inflection Point Engineering, LLC. All rights reserved.