Inflection Point Engineering Section 6 — Rotating Equipment

Centrifugal Pumps Inspection Checklist

IPE Engineering Practice IPE-EP-6-1-1C

Document number: IPE-EP-6-1-1C · Section: 6 — Rotating Equipment

THE MANUFACTURER OF EQUIPMENT PURCHASED BY REFINING COMPANY SHALL BE RESPONSIBLE FOR MEETING ALL APPLICABLE REQUIREMENTS OF THE ENGINEERING PRACTICES AND OTHER DOCUMENTS REFERENCED THEREIN REGARDLESS OF WHETHER THE ITEMS ARE INSPECTED BY A REPRESENTATIVE.

REFERENCES

THE LATEST EDITION OF THE FOLLOWING STANDARDS AND PUBLICATIONS ARE REFERRED TO HEREIN.

ENGINEERING PRACTICES

EP 5-6-2 PIPING FOR ROTATING EQUIPMENT EP 6-1-1 CENTRIFUGAL PUMPS

EP 6-7-1 SPECIAL REQUIREMENTS FOR ROTATING EQUIPMENT EP 15-1-4 POSITIVE MATERIALS IDENTIFICATION (PMI)

API PUBLICATIONS

API 610 CENTRIFUGAL PUMPS

FREQUENCY OF CONTACT BY THE INSPECTOR: (CHECK ONE)

LEVEL 1: ON CALL BY FABRICATOR LEVEL 2: ONCE EVERY TWO WEEKS LEVEL 3: EVERY WEEK

LEVEL 4: DAILY

LEVEL 5: RESIDENT LEVEL 6: OTHER, SPECIFY

LEVEL OF INSPECTION BY THE INSPECTOR: (CHECK ONE)

LEVEL 1: PREFABRICATION MEETING, DOCUMENT REVIEW, AND FINAL INSPECTION

LEVEL 2: PREFABRICATION MEETING, DOCUMENT REVIEW, REVIEW ITEMS, AND FINAL INSPECTION

LEVEL 3: PREFABRICATION MEETING, DOCUMENT REVIEW, REVIEW ITEMS, WITNESS POINTS, AND FINAL

INSPECTION LEVEL 4: PREFABRICATION MEETING, DOCUMENT REVIEW, REVIEW ITEMS, WITNESS POINTS, HOLD POINTS, AND FINAL INSPECTION

LEVEL 5: OTHER, SPECIFY

PUMP CLASS: (CHECK ONE)

CLASS I CLASS II CLASS III CLASS IV

DOCUMENT REVIEW (Shop Inspector Shall Review):

DOCUMENT DESCRIPTION INSPECTOR'S INITIALS (REVIEW COMPLETE) DATE
1. PURCHASE DOCUMENTS
2. DRAWINGS AND SPECIFICATIONS
3. INSTRUCTION MANUAL INCLUDED WITH PUMP
4. QUALITY CONTROL MANUAL
5. QUALITY CONTROL PLAN
6. MATERIAL RECEIVING SIGN-OFF
7. MATERIAL REQUISITIONS ( EP 6-1-1 DATA SHEETS)
8. IMPACT TEST REPORTS ( API 610: 2.11.4.1 )
9. IMPACT TEST REPORTS (API 610: 2.11.4.1 )
10. MATERIAL TEST REPORTS ( API 610: 2.11.2 )
11. MATERIAL HARDNESS TEST REPORTS
12. UT REPORTS OF CASTINGS ( API 610: 4.2.2.3 )
13. UT REPORTS OF FORGINGS ( API 610: 4.2.2.3 )
14. TEST EQUIPMENT CALIBRATION CERTIFICATIONS ( EP 6-1-1: 4.3.1.2 )
15. WELDING PROCEDURE SPECS.
16. WELDER QUALIFICATION RECORDS
17. WELDER TRACEABILITY DOCUMENT
18. NDE PROCEDURES
19. NDE TEST REPORTS
20. NDE PERSONNEL CERTIFICATION
21. MFR. PLAN/SHOP TRAVEL
22. IDENTIFICATION OF CRITICAL DIMENSONS
23. SUB-CONTRACTOR Q/C REPORTS
24. AS-BUILT DATA SHEET
25. TEST PROCEDURES
26. TEST PERFORMANCE CURVES
27. SPECIAL TOOL LIST ( API 610: 6.2.3.g )
28. PRESERVATION, PACKAGING AND SHIPPING PROCEDURES
29. RELIEF VALVE CERTIFICATION
30. AUTHORIZED WAIVERS AND/OR DEVIATIONS REVIEW
31. REVIEW OF SUBORDERS OF UNPRICED PURCHASE ORDERS TO SUBVENDORS FOR COMPLIANCE WITH ENGINEERING PRACTICES
32. NAMEPLATE RUBBINGS AND/OR CODES

GENERAL FABRICATION INSPECTION REQUIREMENTS (Applies To All Fabricated Piping):

R CHECK: THE SHOP INSPECTOR SHALL REVIEW DOCUMENTED RESULTS OF INSPECTION PERFORMED BY VENDOR'S INSPECTION OR SUBCONTRACTED INSPECTOR.

O CHECK: INDICATES THE SHOP INSPECTOR SHALL OBSERVE ITEM DURING MANUFACTURE/INSPECTION. SHOP SHALL NOTIFY INSPECTOR TWO DAYS IN ADVANCE OF MANUFACTURE INSPECTION POINT BUT NEED NOT HOLD PRODUCTION FOR INSPECTION.

W CHECK: INDICATES THE SHOP INSPECTOR SHALL INSPECT ITEM DURING HOLD ON FABRICATION. SHOP SHALL NOTIFY INSPECTOR FIVE DAYS IN ADVANCE OF FABRICATION POINT AND SHALL NOT CONTINUE AFFECTED PRODUCTION UNTIL INSPECTOR PERFORMS INDICATED INSPECTION.

PUMP CATEGORIES PUMP CATEGORIES PUMP CATEGORIES PUMP CATEGORIES INSPECTION/TESTING ACTIVITY INSPECTOR'S INITIALS DATE
I II III IV
1. R R NAMEPLATE REQUIREMENTS (API 610: 2.12, EP 6-1-1: 2.12.2)
2. R W HYDROSTATIC TEST (API 610: 4.3.2)
3. R W W PERFORMANCE TEST (API 610: 2.1.26, 4.3.3:, EP 6-1-1: 2.8.4)
4. R W W NPSH TEST (API 610: 4.3.1.1, 4.3.4.1)
5. R W W PREPARATION FOR SHIPMENT (API 610: 2.7.1.15, 4.4:, EP 6-1-1:
4.4:, EP 6-7-1: 6.0)
6. R R R R SPARE PART LIST COMPLETE (API 610: 5.1.1, 5.2.5.7: EP 6-1-1:
5.1.1)
7. R R R R LUBRICATION REQUIREMENT (EP 6-7: 8.0)
8. PMI OF ALL APPLICABLE MATERIALS
9. CASTINGS REPAIR PROCEDURE APPROVED (API 610: 2.11.2.3)
10. NDE OF CASTINGS (API 610: 2.11.2: 4.2.2.2-5)
11. NDE OF NOZZLES IN CASTINGS (API 610: 2.1.3.3: 4.2.2.2-5)
12. NDE CONNECTIONS WELDED TO CASINGS (API 610: 2.1.3.7: 4.2.2.2-5)
13. RT LOCATION SELECTION
14. RADIOGRAPH REVIEW (API 610: 4.2.2.2-5)
15. R O W W NDE OF REPAIRS
16. REVIEW OF COLD WORKED PARTS PWHT
17. FLATNESS CHECK OF GASKET CONTACT SURFACES AFTER PWHT
18. HARDNESS TEST (API 610: 2.11.1.10; EP 10-2-3)
19. CHAPPY IMPACT TEST (API 610: 2.11.1.13)
20. R COUPLING DYNAMIC BALANCE (API 610: 3.2.7)
21. O O ROTOR DYNAMIC BALANCING (API 610: 2.8.4.1-5)
22. O RESIDUAL UNBALANCE CHECK (API 610: 2.8.4.6, APPENDIX J)
23. SURFACTANT HYDROTEST (API 610: 4.3.2.5)
24. W W COMPLETE UNIT MECHANICAL RUNNING TEST (API 610: 4.3.4.2)
25. R R O W SOUND LEVEL TEST (API 610: 4.3.4.2)
26. PIPELOAD TEST (API 610: 3.3.1.6)
27. AUXILIARY-EQUIPMENT TEST (API 610: 4.3.4.4)
28. W DISMANTLE AND INSPECTION AFTER TEST (API 610: 4.3.3.4.3)
29. O W W W CLEANLINESS PRIOR TO FINAL ASSEMBLY (API 610: 4.2.3.1)
30. FINAL INSPECTION AND APPROVAL BEFORE SHIPPING
31.
32.
33.
PUMP CATEGORIES PUMP CATEGORIES PUMP CATEGORIES PUMP CATEGORIES INSPECTION/TESTING ACTIVITY INSPECTOR'S INITIALS (REVIEW COMPLETE) DATE
I II III IV INSPECTION/TESTING ACTIVITY INSPECTOR'S INITIALS (REVIEW COMPLETE) DATE
WELDING INSPECTION WELDING INSPECTION WELDING INSPECTION WELDING INSPECTION WELDING INSPECTION WELDING INSPECTION WELDING INSPECTION WELDING INSPECTION
1. R R WELDING REQUIREMENTS ( API 610: 2.3.3.4, 5 & 6; 2.11.3,
3.3.7, 3.5.1.10, 3.5.,5.5; EP 6-1-1: 2.11.3.6)
2. R R WELDER PERFORMANCE QUALIFICATION (API 610: 2.11.3.1)
3. R R WELDER IDENTIFICATION
4. R R PWHT REQUIREMENTS (API 610: 2.11.3.2, 2.11.3.4.4, 2.11.3.5.5)
5. R R WELD HARNESS REQUIREMENTS (API 610: 4.2.3.2)
6. W W WELDING REPAIRS (API 610: 2.11.2.3.1, 2.11.3.1; EP 6-1-
1:2.11.2.3)
7. R R WELDING REPAIR APPROVED
8. R R WELDING REPAIR MAPS
9. R R PWHT PROCEDURE APPROVED
10.
11.
12.
13.
MANUFACTURING CHECKS MANUFACTURING CHECKS MANUFACTURING CHECKS MANUFACTURING CHECKS MANUFACTURING CHECKS MANUFACTURING CHECKS MANUFACTURING CHECKS MANUFACTURING CHECKS
14. VERIFY ASSEMBLY IS PER APPROVED DRAWING AND PARTS LIST
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
PUMP CATEGORIES PUMP CATEGORIES PUMP CATEGORIES PUMP CATEGORIES INSPECTION/TESTING ACTIVITY INSPECTOR'S INITIALS (REVIEW COMPLETE) DATE
I II III IV INSPECTION/TESTING ACTIVITY INSPECTOR'S INITIALS (REVIEW COMPLETE) DATE
DIMENSION CHECKS DIMENSION CHECKS DIMENSION CHECKS DIMENSION CHECKS DIMENSION CHECKS DIMENSION CHECKS DIMENSION CHECKS DIMENSION CHECKS
1. R GENERAL ( API 610: 2.10.2 )
2. R PRESSURE CASINGS ( API 610: 2.2.10 )
3. R NOZZLES & PRESSURE CASINGS CONNECTIONS ( API 610: 2.3.1.2;2.3.2.6, 2.3.3.6 )
4. R ROTATING ELEMENTS ( API 610: 2.5.4, 5, 6, 7, 8, 10, EP 6-1-1:
2.5.8 )
5. R WEAR RINGS ( API 610: 2.6.3, 4 )
6. R SEALS ( API 610: 2.7.3.6, 13, 14, 15 )
7. R BEARINGS &BEARING HOUSINGS ( API 610: 2.9.2.2,7 )
8. R COUPLINGS & GUARDS ( API 610: 5.3.7.2 )
9. R BASE PLATES ( API 610: 3.3, RP 12-1-1: 3.3.1 )
10. R PIPING & APPURTENANCES ( API 610: 3.5.1.8, 9,10, 11, 12, 14 )
11.
12.
13.
14.
INSTRUMENTATION INSPECTION INSTRUMENTATION INSPECTION INSTRUMENTATION INSPECTION INSTRUMENTATION INSPECTION INSTRUMENTATION INSPECTION INSTRUMENTATION INSPECTION INSTRUMENTATION INSPECTION INSTRUMENTATION INSPECTION
15. R TEMPERATURE GAUGES (API 610: 3.4.1)
16. R THERMOWELLS
17. PRESSURE GAUGES (API 610: 3.4.2)
18. VIBRATIONS &TEMPERTURE DETECTIONS (API 610: 3.4.3; API 670)
19.
20.
21.
22.
MISCELLANEOUS MISCELLANEOUS MISCELLANEOUS MISCELLANEOUS MISCELLANEOUS MISCELLANEOUS MISCELLANEOUS MISCELLANEOUS
23. R R R R EPOXY GROUTING PREPARATION (API 610: 3.3.17)
24. SPECIAL TOOLS (API 610: 3.6)
25.
26.
INSPECTOR SIGN-OFF INSPECTOR SIGN-OFF INSPECTOR SIGN-OFF INSPECTOR SIGN-OFF
INITIALS NAME COMPANY SOCIAL SECURITY NUMBER
SUMMARY: