Section 6 — Rotating Equipment
IPE Engineering Practice IPE-EP-6-1-1
Document number: IPE-EP-6-1-1 · Section: 6 — Rotating Equipment
The following paragraph numbers refer to API 610, 8th Edition, August 1995, titled, "Centrifugal Pumps for Petroleum, Heavy Duty Chemical, and Gas Industry Services," which is part of this Engineering Practice.
Table 1 records the vendor drawing and data requirements.
The following additional terms are used in this standard.
1.5 Referenced Publications
1.5.4 The referenced Engineering Practices, and any other attached to the requisition shall apply to the extent referenced herein or on the Data Sheets. The Data Sheets and Inspection Checklists from API 610 shall be used in conjunction with this document.
| Engineering Practices |
|---|
| EP 1-1-3 Deviations to Engineering Practices EP 2-5-2 Documentation Format Requirements EP 4-2-9 Grouting and Base Plates for Structural Steel and Equipment EP 5-3-6 Compact and Extended Body Gate and Globe Valves EP 5-5-1 Piping Fabrication EP 5-6-2 Piping for Rotating Equipment EP 6-3-1 General Purpose Steam Turbines EP 7-1-2 Pressure Vessels for Non-Process Services EP 8-1-2 TEMA Shell and Tube Heat Exchangers for Non-Process Services EP 13-3-1 Induction Motors 500 HP and Below EP 13-3-2 Induction Motors Above 500 HP EP 13-3-3 Synchronous Motors |
| ASME Codes |
| Sec VIII Pressure Vessels, Section VIII, Division 1 B31.3 Process Piping |
| API Publications |
| Std 610 Centrifugal Pumps for Petroleum, Heavy Duty Chemical, and Gas Industry Services |
2.1.9 (*) Pump suction specific speed (NSS) shall not exceed 12,000 (calculated using rotative speed in rev/min, flow in GPM, and NPSH In feet) without written approval of the Owner's Engineer. See paragraph 1.4.49.
2.1.11 (*) a. The head curve for the pump shall be continuously rising from the specified capacity point to the shutoff point. The pump head at shutoff shall be between 110 and 120 percent of the head at the specified capacity point. Pumps whose shutoff head exceeds 120 percent of the head at the specified capacity point may be submitted for approval by the Owner's Engineer. Written approval by the Owner's Engineer is required to apply a discharge orifice as a means of providing a continuous rise to shutoff.
b. Pumps for parallel operation shall have equal head rise to shutoff.
(*) c. Low capacity, high-head pumps may be exempt from the requirements of 2.1.11.a and
2.1.11.b with the approval of the Owner's Engineer.
2.1.14 The maximum allowable sound pressure level is 85 dBA measured at 3 feet from any equipment surface. Test data on similar pumps shall be made available upon request.
2.1.17 Pumps shall be designed to operate continuously without the use of cooling water.
2.2 Pressure Casings
2.2.4 Areas of vertically suspended, double-case and horizontal multistage pumps which are normally subjected to suction pressure shall be designed to the same pressure as discharge areas of the pump.
2.2.14 (*) Vertical turbine pumps shall have columns and bowls of the bolted design. Screwed bowl sections may be supplied only if specifically approved by the Owner.
2.3 Nozzles and Pressure Casing Connections
2.3.2 Suction and Discharge Nozzles
2.3.2.1 (Exception) All pumps shall have suction and discharge flanges of equal rating. The ANSI permissible hydrostatic test pressure of suction flanges shall be equal to, or greater than, the pump casing hydrostatic test pressure.
2.3.3.10 a. All vents and drains shall be valved, either flanged or socket welded.
2.3.3.12 a. Valved vent and drain connections shall comply with the requirements of EP 5-5-1.
b. Valves for vents, drains, and clean-out connections shall be as follows:
2.5.7 (Exception) The shaft stiffness for all pumps shall limit the total shaft deflection under the most severe conditions over the complete head-capacity curve to .002 inch at the face of the stuffing box or seal chamber and to less than one-half the minimum diametrical clearance at all bushings and wear rings. The shaft shall be designed to transmit momentarily at least four times the rated torque of the pump driver.
2.8 Dynamics
2.8.1.1 Full rotordynamic (lateral and Torsional) analysis are required for pumps exceeding 4000 RPM (except OHG) or 1000 HP.
2.8.2.6 If a torsional analysis is required per paragraph 2.8.2.1, a detailed report shall be furnished.
2.8.3 Vibration
2.8.3.10 The Vendor shall demonstrate that the pump can operate at any capacity from 120 percent of the rated capacity to the quoted minimum continuous stable flow without exceeding the vibration limits given in paragraph 2.8.3.7.
2.9 Bearings and Bearing Housings
2.9.1 Bearings
2.9.1.5 a. Ball-type thrust bearings shall have machined brass cages. The vendor shall verify the adequacy of duplex, single-row, 40 degree (0.7 radian) angular-contact type (7000-series) bearings, installed back-to-back. This verification shall include selection of proper axial and radial (shaft interference fit-related) preload values to prevent skidding of the unloaded bearing over the entire operating range of the pump.
2.9.2 Bearing Housings
2.9.2.2 The constant-level lubricators shall be Trico Optimatic, or Owner-approved equivalent fully balanced type, and installed with the stainless steel balance line entering the bearing housing at the former vent connection, i.e. at the top of the bearing housing (Note that there shall be
no bearing housing vent). The lubricator shall be at the "up arrow" side of the bearing housing, as recommended by TRICO Mfg. Company
2.9.2.6 The vendor shall provide INPRO style VBX bearing isolators at all bearing housings.
2.11.1.1 Twelve percent chrome castings shall be per ASTM A487, Grade CA6NM.
Austenitic stainless steel shall be per ASTM A351 with liquid penetrant examination to S.6. Monel Castings shall be per ASTM A494 grade M-30C with weldability test S.2. and liquid penetrant examination S.5.
2.11.2.2 Chaplets in casings other than cast iron that are not completely fused into pressure castings or other defects shall be replaced by weld metal equivalent to the casing composition. No other repair method is permitted. Casings shall be heat treated following any major repairs.
2.11.3.5.5 PWHT is required for all carbon and ferritic alloy steel pressure-containing components that are welded and/or weld repaired, when the weldment is exposed to a process containing wet H2S. The PWHT procedure outlined in ASME Code Section VIII, paragraphs UW40, UW49, UHA32, and UCS56 shall be followed, except that the notes in Tables UHA32 and UCS56 do not apply. All welds, regardless of type or size, that are exposed to wet H2S shall be PWHT at a minimum temperature of 1150 oF. External attachments or seal welded threaded connections on P-1 Group 1 and 2 materials do not require PWHT.
(Exception) Pressure casing components, either cast, forged, or welded, shall meet the following impact requirements:
| CET (oF) | Maximum Casing Working Pressure | Impact Requirements (1) |
|---|---|---|
| 20 oF | All | 15/12 ft-Ibf |
| 20 oF to < 60 oF | > 1000 psi | 15/12 ft-Ibf |
| 20 oF to < 60 oF | ~1000 psi | None |
| 60 oF | All | None |
(*) c. All impact test details shall be approved by the Owner's Engineer.
3.1.1 Unless otherwise specified, drivers shall be induction motors designed per EP 13-3-1, if 500 HP or smaller, and per EP 13-3-2, if larger than 500 HP. Synchronous Motors shall be in accordance with EP 13-3-3.
300 HP and 350 HP - copper bars if intermittent duty 350 HP and smaller - cast aluminum
3.1.9 Steam turbines shall conform to EP 6-3-1, unless otherwise specified.
3.1.13 For vertical pumps, the Vendor shall assemble, align and dowel the motor or gear to the pump in its shop to assure proper unit fit-up and shaft mating.
3.2 Couplings and Guards
3.2.2 When the coupling type is not specified by the Owner, a Rexnord Thomas Series 71 nonlubricated disc type coupling with stainless steel disc packs shall be supplied by the pump Vendor.
3.2.8.1 API 671 applies to applications over 750 HP and for unspared critical machines.
3.2.12 Coupling guards for horizontal pumps shall be fabricated from aluminum or molded from rigid OSHA-approved orange-color polyurethane. Guards shall be provided with a hinged door for inspection of coupling flexible elements.
3.3.14 Alignment positioning jackscrews shall be provided for all equipment feet, regardless of equipment weight.
3.3.21 Mounting plates for vertical pumps shall be per the following:
3.3.21.1 Double-casing vertical pumps shall have a steel mounting plate that completely surrounds the outer casing and is attached to it by a continuous weld. The steel mounting plate shall have a 3/4 inch (22 mm) pipe connection to vent the space between the outer barrel and the foundation. The plate shall be rectangular with radiused corners. Foundation bolts shall not be used to secure the flanged pressure-casing joint.
3.4.3 Provide vibration probes per paragraph 3.4.3.1 and bearing RTDs per paragraph 3.4.3.2 on pump trains exceeding 1000 HP and/or 4000 RPM, and on all unspared critical trains.
3.5.1 General
3.5.1.4 Barrier/buffer fluid reservoirs shall be designed for mounting off the pump baseplate and shall be supplied by the Purchaser along w\ith connecting tubing and instrumentation.
3.5.1.9 Threaded or slip on flanges are not acceptable.
3.5.1.15 Threaded connections shall be made up without the use of PTFE tape.
3.5.2 Auxiliary Process Fluid Piping
3.5.2.7 All orifice plates shall be installed in flanged connections and have a tab, marked with the orifice size, extending from the flange where they are installed to indicate their location.
3.5.2.10.1 Flanges are required.
3.5.2.11 (*) Mechanical seal flush lines in Flammable or Hazardous service shall be piped unless tubing is approved by the Owner's Engineer.
3.7 (New Section) Pressure Vessels and Heat Exchangers
(*) Unless otherwise approved by the Owner's Engineer, pressure vessels and heat exchangers associated with rotating equipment shall be designed, fabricated, inspected and tested in accordance with EP 7-1-2 and EP 8-1-2.
4.2.1.3 As a minimum, inspection shall include: verification of the equipment dimensions, compliance with baseplate machining tolerances, examination of test data and checking preparation for shipment. For services with pumping temperatures 500oF or higher, the Inspector shall verify that the internal clearances conform to 2.6.4.2.
4.2.2.1 Pressure boundary components of pumps in flammable or toxic service shall be inspected per the requirements of paragraph 4.2.2.4 (magnetic particle inspection) or paragraph 4.2.2.2 (radiography).
| Inspection or test | Required | Witnessed | Certified Data |
|---|---|---|---|
| Hydrostatic Test | Yes | No (1) | Yes |
| Performance Test | Yes | No (2) | Yes |
| NPSH Test | (3) | (3) | Yes |
| Inspection by Purchaser | (4) | ||
| Dismantled Inspection | (5) |
(*) (3) If the NPSH required for the pump differs from the specified available NPSH by 6 feet or less, an NPSH suppression and performance test is required. For pumps requiring NPSH testing, the test of one pump in each service shall be witnessed by the Inspector. For the balance of identical pumps, witness is not required; however, certification of test results is required.
(*) (5) Each sleeve bearing pump receiving a witnessed performance test shall have a witnessed bearing inspection by the Inspector following the final performance test.
c. Mechanical seal flushing liquid coolers shall be hydrostatically tested to at least the same pressure as the pump casing.
4.3.3.2.1 All pumps shall be operated for at least one hour at rated speed and capacity. One of the data points shall be the rated point.
(*) When specified by the Owner's Engineer, the seal chamber pressure shall be measured at each point during the performance test. The Vendor shall ensure that the measured seal chamber pressures, when corrected for rated suction pressure and specific gravity, are consistent with those assumed in designing the mechanical seal (see 2.7.1.12). Corrective steps needed to improve the seal design or seal chamber conditions shall be mutually agreed upon by the Vendor and Owner's Engineer.
4.3.3.3.3 (*) (Exception) In no case shall the minus tolerance allowance for shutoff head exceed two percent. The shutoff head with the positive tolerance allowance included shall not exceed 120 percent of the head at the rated capacity, unless previously approved by the Owner's Engineer.
4.4 Preparation for Shipment
4.4.3.4 (Exception) Unless otherwise specified, the rust preventive applied to unpainted exterior machined surfaces shall be of a type: (1) to provide protection during outdoor storage for a period of 12 months exposed to a normal industrial environment, and (2) to be removable with mineral spirits or any Stoddard solvent.
5.2.6 Lubrication
5.2.6.2 b. Materials of construction for coolers in salt water cooling service shall be as follows:
| Item | Material Description |
|---|---|
| Tubes | ASME SB338 Gr. 2 Titanium |
| Tubesheets | Carbon steel with SB265 Gr. 1 titanium cladding on tube side (1/2 inch minimum thickness after machining) |
| Baffles, Tie-Rods & Spacers | Carbon steel |
| Channel | AL-6XN with 1/16 inch corrosion allowance for barrel and partitions with carbon steel slip-on flanges, gasket surfaces weld overlaid with 1/4 inch Inconel 625 |
| Channel Cover | Carbon steel with Gr. 1 titanium cladding (5/16 inch minimum thickness after machining) |
| Floating Head | Carbon steel with 1/4 inch minimum thickness Inconel 625 weld overlay on wetted surface, pass partitions of Inconel 625 |
| Shell | Carbon steel |
5.2.6.4 Lube oil pumps shall be IMO screw-type. Pumps enclosed in the lube-oil reservoir shall have stell or ductile iron cases.
5.3 Vertically Suspended Pumps
5.3.7.3.5 A separate sole plate is required. The underside shall be prepared for epoxy grout.
Quoted efficiency and power shall take into account the increased clearance required for hot pumps.
6.3.2 Drawings
Cross-sectional dimensioned drawings of the stuffing box, seal, gland, shaft sleeve, and proposed flushing arrangement for the mechanical seal shall be provided.
Unless exception is recorded by the Vendor in his proposal, it shall be understood that the Vendor agrees to the guarantees and warranties specified in Items 1 and 2 below:
The equipment shall be guaranteed for satisfactory performance at all operating conditions specified on the data sheet. Field checks on performance, when made by the Purchaser, shall be made within 60 days of initial operation
| Item | Description | Format (1) | As-Built |
|---|---|---|---|
| 1 | Certified dimensional outline drawing | See EP 2-5-2 | Yes |
| 2 | Cross-sectional drawing and bill of materials | See EP 2-5-2 | Yes |
| 3 | Shaft seal drawing and bill of materials | See EP 2-5-2 | Yes |
| 4 | Coupling assembly drawing and bill of materials | See EP 2-5-2 | Yes |
| 5 | Primary and auxiliary sealing schematic and bill of materials | See EP 2-5-2 | Yes |
| 6 | Cooling or heating schematic and bill of materials | See EP 2-5-2 | Yes |
| 7 | Lube-oil schematic and bill of materials | See EP 2-5-2 | Yes |
| 8 | Lube-oil system arrangement drawing and list of connections | See EP 2-5-2 | Yes |
| 9 | Lube-oil component drawings and data | See EP 2-5-2 | Yes |
| 10 | Electrical and instrumentation schematics and bill of materials | See EP 2-5-2 | Yes |
| 11 | Electrical and instrumentation arrangement drawing and list of connections | See EP 2-5-2 | Yes |
| 12 | Performance curves | See EP 2-5-2 | Yes |
| 13 | Vibration analysis data | See EP 2-5-2 | Yes |
| 14 | Damped unbalanced response analysis | See EP 2-5-2 | Yes |
| 15 | Lateral critical speed analysis | See EP 2-5-2 | Yes |
| 16 | Torsional critical speed analysis | See EP 2-5-2 | Yes |
| 17 | Certified hydrostatic test data | See EP 2-5-2 | Yes |
| 18 | Weld procedures | See EP 2-5-2 | Yes |
| 19 | Performance test data | See EP 2-5-2 | Yes |
| 20 | Certified rotor balance data for multistage pumps | See EP 2-5-2 | Yes |
| 21 | Residual unbalance check | See EP 2-5-2 | Yes |
| 22 | Rotor mechanical and electrical runout | See EP 2-5-2 | Yes |
| 23 | Data Sheets | See EP 2-5-2 | Yes |
| 24 | Clearances | See EP 2-5-2 | Yes |
| 25 | Installation, operation, and maintenance manuals | See EP 2-5-2 | Yes |
| 26 | Spare parts recommendations | See EP 2-5-2 | Yes |
(1) (*) If the document cannot be provided in the format as indicated, the Manufacturer shall consult with the Owner's Engineer for an acceptable alternative.
© 2026 Inflection Point Engineering, LLC. All rights reserved. The content of this page — including calculation methods, reference data, written analysis, interactive tools, and source code — is the intellectual property of Inflection Point Engineering, LLC and is protected under applicable copyright, trademark, and trade secret laws. Unauthorized reproduction, redistribution, modification, or derivative use in whole or in part is prohibited without prior written consent.
Disclaimer. This material is provided for informational and educational purposes only and does not constitute professional engineering advice. Calculations, reference data, and methodologies are based on published standards and accepted engineering practice but are not a substitute for engineering judgment, site-specific analysis, or review by a licensed Professional Engineer. Inflection Point Engineering, LLC makes no warranties, express or implied, regarding the accuracy, completeness, or fitness for a particular purpose of any content presented here, and shall not be liable for any direct, indirect, incidental, or consequential damages arising from its use. Users assume all risk associated with applying this content to real-world design, operations, or decisions.
© 2026 Inflection Point Engineering, LLC. All rights reserved.