Section 4 — Structures and Foundations
IPE Engineering Practice IPE-EP-4-8-1C
Document number: IPE-EP-4-8-1C · Section: 4 — Structures and Foundations
THE MANUFACTURER OF EQUIPMENT PURCHASED BY INFLECTION POINT ENGINEERING, LLC SHALL BE RESPONSIBLE FOR MEETING ALL APPLICABLE REQUIREMENTS OF THE IPE ENGINEERING PRACTICES AND OTHER DOCUMENTS REFERENCED THEREIN REGARDLESS OF WHETHER THE ITEMS ARE INSPECTED BY A IPE REPRESENTATIVE.
THE LATEST EDITION OF THE FOLLOWING STANDARDS AND PUBLICATIONS ARE REFERRED TO HEREIN.
EP 4-8-1 SEWER SYSTEMS
EP 4-8-2 TYPICAL SEWER DETAILS
LEVEL 2: PREFABRICATION MEETING, DOCUMENT REVIEW, REVIEW ITEMS, AND FINAL INSPECTION LEVEL 3: PREFABRICATION MEETING, DOCUMENT REVIEW, REVIEW ITEMS, WITNESS POINTS, AND FINAL
LEVEL 4: PREFABRICATION MEETING, DOCUMENT REVIEW, REVIEW ITEMS, WITNESS POINTS, HOLD POINTS, AND FINAL INSPECTION
R CHECK: THE SHOP INSPECTOR SHALL REVIEW DOCUMENTED RESULTS OF INSPECTION PERFORMED BY VENDOR'S INSPECTION OR SUBCONTRACTED INSPECTOR.
W CHECK: INDICATES THE SHOP INSPECTOR SHALL WITNESS ITEM DURING FABRICATION. SHOP SHALL NOTIFY INSPECTOR TWO DAYS IN ADVANCE OF FABRICATION POINT BUT NEED NOT HOLD PRODUCTION FOR INSPECTION.
H CHECK: INDICATES THE SHOP INSPECTOR SHALL INSPECT ITEM DURING HOLD ON FABRICATION. SHOP SHALL NOTIFY INSPECTOR FIVE DAYS IN ADVANCE OF FABRICATION POINT AND SHALL NOT CONTINUE AFFECTED PRODUCTION UNTIL INSPECTOR PERFORMS INDICATED INSPECTION.
| R | W | H | INSPECTION/TESTING ACTIVITY | INSPECTOR'S INITIALS (REVIEW COMPLETE) | DATE |
|---|---|---|---|---|---|
| MANHOLES AND CATCH BASIN NUMBER AND LOCATION COMPLY WITH DRAWINGS AND EP 4-8-1: 9.1, 9.2 | |||||
| FIRESEALS COMPLY WITH DRAWINGS AND EP 4-8-1: 9.3 | |||||
| CLEANOUTS COMPLY WITH DRAWINGS AND EP 4-8-1: 9.4 | |||||
| SEWERS ARE VENTED IN ACCORDANCE WITH DRAWINGS AND EP 4-8-1: 9.5 | |||||
| MATERIALS FOR SEWERS COMPLY WITH DRAWINGS AND EP 4-8-1: 10.0 | |||||
| INVERTS AND ELEVATIONS COMPLY WITH DRAWINGS AND EP 4-8-1: 11.1 | |||||
| INSTALLED COMPONENTS COMPLY WITH DETAILS IN EP 4-8-2 | |||||
| TRENCHES EXCAVATED TO PRESCRIBED DIMENSIONS AND ELEVATIONS (EP 4-8-1:11.1) | |||||
| TRENCH CONDITION SUITABLE FOR PIPE INSTALLATION (EP 4-8-1: 11.1) | |||||
| TRENCH BACKFILL ACCEPTABLE TO OWNER (EP 4-8-1: 11.1) | |||||
| BACKFILL INSTALLED PER EP 4-8-1: 11.1 | |||||
| THRUST BLOCKS AND CROSSINGS INSTALLED PER EP 4- 8-1: 11.1 AND DRAWING (EP 4-8-1: 11.1) | |||||
| JOINTS PROTECTED AT END OF WORK DAY (EP 4-8-1: 11.1) | |||||
| LINES PROPERLY PREPARED FOR TESTING (EP 4-8-1: 11.1) | |||||
| SANITARY SEWERS COMPLY WITH JURISDICTIONA AND EP 4-8-1: 11.2 | |||||
| EXFILITRATION OR HYDROTEST PERFORMED PER EP 4-8- 1: 12.0 | |||||
| LINES PROPERLY FLUSHED (EP4-8-1: 13.0) | |||||
AS A MINIMUM, THE FOLLOWING LEVELS OF INSPECTION SHALL BE PERFORMED:
P CHECK: CHECK PRIOR TO STARTING WORK ON EACH SHIFT
R CHECK: IN ADDITION TO "P" CHECK, MAKE RANDOM CHECKS DURING SHIFT
| READINGS | READINGS | ||
|---|---|---|---|
| TIME | VALUE | ||
| P | TRENCH CONDITIONS (11.1) | ||
| P | END OF DAY JOINT PROTECTION (11.1.6) | ||
| INSPECTOR SIGN-OFF | INSPECTOR SIGN-OFF | INSPECTOR SIGN-OFF | INSPECTOR SIGN-OFF |
|---|---|---|---|
| INITIALS | NAME | COMPANY | SOCIAL SECURITY NUMBER |
| SUMMARY: |
|---|
© 2026 Inflection Point Engineering, LLC. All rights reserved. The content of this page — including calculation methods, reference data, written analysis, interactive tools, and source code — is the intellectual property of Inflection Point Engineering, LLC and is protected under applicable copyright, trademark, and trade secret laws. Unauthorized reproduction, redistribution, modification, or derivative use in whole or in part is prohibited without prior written consent.
Disclaimer. This material is provided for informational and educational purposes only and does not constitute professional engineering advice. Calculations, reference data, and methodologies are based on published standards and accepted engineering practice but are not a substitute for engineering judgment, site-specific analysis, or review by a licensed Professional Engineer. Inflection Point Engineering, LLC makes no warranties, express or implied, regarding the accuracy, completeness, or fitness for a particular purpose of any content presented here, and shall not be liable for any direct, indirect, incidental, or consequential damages arising from its use. Users assume all risk associated with applying this content to real-world design, operations, or decisions.
© 2026 Inflection Point Engineering, LLC. All rights reserved.