Section 4 — Structures and Foundations
IPE Engineering Practice IPE-EP-4-5-2C
Document number: IPE-EP-4-5-2C · Section: 4 — Structures and Foundations

| EQUIPMENT ID | JOB NO. | DOCUMENT NO. | REV. |
|---|
THE MANUFACTURER OF EQUIPMENT PURCHASED BY REFINING COMPANY SHALL BE RESPONSIBLE FOR MEETING ALL APPLICABLE REQUIREMENTS OF THE ENGINEERING PRACTICES AND OTHER DOCUMENTS REFERENCED THEREIN REGARDLESS OF WHETHER THE ITEMS ARE INSPECTED BY A REPRESENTATIVE.
THE LATEST EDITION OF THE FOLLOWING STANDARDS AND PUBLICATIONS ARE REFERRED TO HEREIN.
EP 4-5-1 STRUCTURAL STEEL
EP 4-5-2 STRUCTURAL STEEL CONSTRUCTION
EP 4-5-3 AUXILIARY STRUCTURES FOR OPERATION AND MAINTENANCE EP10-3-2 FIELD PAINTING
SPECIFICATION FOR THE DESIGN, FABRICATION AND ERECTION OF STRUCTURAL STEEL FOR BUILDINGS CODE OF STANDARD PRACTICE FOR STEEL BUILDINGS AND BRIDGES
SPECIFICATION FOR STRUCTURAL JOINTS USING ASTM A325 OR A490 BOLTSEP 4-3-1 CONCRETE DESIGN
LEVEL 2: PREFABRICATION MEETING, DOCUMENT REVIEW, REVIEW ITEMS, AND FINAL INSPECTION LEVEL 3: PREFABRICATION MEETING, DOCUMENT REVIEW, REVIEW ITEMS, WITNESS POINTS, AND FINAL
LEVEL 4: PREFABRICATION MEETING, DOCUMENT REVIEW, REVIEW ITEMS, WITNESS POINTS, HOLD POINTS, AND FINAL INSPECTION
| EQUIPMENT ID | JOB NO. | DOCUMENT NO. | REV. |
|---|
R CHECK: THE SHOP INSPECTOR SHALL REVIEW DOCUMENTED RESULTS OF INSPECTION PERFORMED BY VENDOR'S INSPECTION OR SUBCONTRACTED INSPECTOR.
W CHECK: INDICATES THE SHOP INSPECTOR SHALL WITNESS ITEM DURING FABRICATION. SHOP SHALL NOTIFY INSPECTOR TWO DAYS IN ADVANCE OF FABRICATION POINT BUT NEED NOT HOLD PRODUCTION FOR INSPECTION.
H CHECK: INDICATES THE SHOP INSPECTOR SHALL INSPECT ITEM DURING HOLD ON FABRICATION. SHOP SHALL NOTIFY INSPECTOR FIVE DAYS IN ADVANCE OF FABRICATION POINT AND SHALL NOT CONTINUE AFFECTED PRODUCTION UNTIL INSPECTOR PERFORMS INDICATED INSPECTION.
| R | W | H | INSPECTION/TESTING ACTIVITY | INSPECTOR'S INITIALS (REVIEW COMPLETE) | DATE |
|---|---|---|---|---|---|
| VERIFICATION OF COMPLETE AND CORRECT ERECTION DRAWINGS (EP 4-5-1: 6.1) | |||||
| MILL TEST REPORT VERIFICATION (EP 4-5-2: 4.7) | |||||
| WELD FILLER METAL CONFORMITY CERTIFICATION (EP 4-5-2: 4.4) | |||||
| BOLTING MATERIAL CONFORMITY CERTIFICATION (EP 4-5-1: 4.3) | |||||
| FABRICATION IN ACCORDANCE WITH AISC (EP 4-5-2: 4.1) | |||||
| COLUMNS MACHINED FOR LULL BEARING (EP 4-5-2: 4.1) | |||||
| GALVANIZING IN ACCORDANCE WITH EP 4-5-2: 4.5 | |||||
| ERECTION MARKS IN ACCORDANCE WITH EP 4-5-2: 4.1 | |||||
| FIREPROOFING CLIPS IN ACCORDANCE WITH EP 4-5-2: 4.1 | |||||
| ONE-SIDED BEAM CONNECTIONS PER EP 4-5-2: 4.3 | |||||
| BOLTS AND WASHERS SUPPLIED PER EP 4-5-2: 4.3 | |||||
| ALL REQUIRED ERECTION PLATES AND ANGLES SUPPLIED (EP 4-5-2: 4.3) | |||||
| TORQUE VALUES FOR BOLTED CONNECTIONS APPROVED (EP 4-5-2: 4.3) | |||||
| AUXILIARY STRUCTURE MATERIALS PER EP 4-5-1: 4.4, 4.5, EP 4-5-3 |
|||||
| AUXILIARY STRUCTURE CONNECTIONS PER EP 4-5-2: 4.3 | |||||
| WELDING PROCEDURES AND QUALIFICATIONS SUBMITTED (EP 4-5-2: 4.4) | |||||
| ALL WELDS COMPLETE PENETRATION UNLESS OTHERWISE NOTED (EP 4-5-2: 4.4) | |||||
| WELDED CONNECTIONS TO BE GALVANIZED COMPLETELY SEAL WELDED (EP 4-5-2: 4.4) | |||||
| FIELD WELDS PROPERLY PREPARED AND PREFIT (EP 4-5-2: 4.4) | |||||
| WELD REPAIRS APPROVED (EP 4-5-2:4.4) | |||||
| HIGH STRENGTH BOLTED CONNECTIONS PER AISC (EP 4-5-2: 4.6) | |||||
| NDE OF SHOP WELDS PER EP 4-5-2:4.6 | |||||
| STEEL PACKAGED AND SHIPPED PER EP 4-5-2: 4.8 | |||||
| ERECTION IN ACCORDANCE WITH AISC AND ERECTION DRAWINGS (EP 4-5-2: 5.1) |
| COLUMN PLUMBNESS AND T.O.S. COMPLY WITH EP 4-5-2: 5.1 | |||||
|---|---|---|---|---|---|
| FIT-UPS ERRORS REQUIRING SPECIAL ATTENTION BROUGHT TO OWNER'S ENGINEER'S ATTENTION (EP 4-5-2: 5.2) | |||||
| FIELD HOLES REQUIRING BURNING APPROVED BY OWNER'S ENGINEER (EP 4-5-2: 5.3) | |||||
| FIELD PAINTING PER EP 14-1-1 | |||||
| NDE OF FIELD WELDS PER EP 4-5-2:5.6 | |||||
| MATERIAL HANDLING AND STORAGE PER EP 4-5-2: 5.7 | |||||
| EQUIPMENT ID | JOB NO. | DOCUMENT NO. | REV. |
|---|
EP 4-3-2 C CONCRETE INSPECTION DAILY LOG SHEET
AS A MINIMUM, THE FOLLOWING LEVELS OF INSPECTION SHALL BE PERFORMED:
P CHECK: CHECK PRIOR TO STARTING WORK ON EACH SHIFT
R CHECK: IN ADDITION TO "P" CHECK, MAKE RANDOM CHECKS DURING SHIFT
| READINGS | READINGS | ||
|---|---|---|---|
| TIME | VALUE | ||
| P | FIELD WELDS (5.4, 5.6) | ||
| P | FIELD CONNECTIONS (5.3, 5.6) | ||
| P | FIELD PAINTING (5.5) | ||
| R | FABRICATION ERRORS (5.2) | ||
| P | JOBSITE SAFETY (5.1) | ||
| P | MATERIAL STORAGE (5.7) | ||
| INSPECTOR SIGN-OFF | INSPECTOR SIGN-OFF | INSPECTOR SIGN-OFF | INSPECTOR SIGN-OFF |
|---|---|---|---|
| INITIALS | NAME | COMPANY | SOCIAL SECURITY NUMBER |
| EQUIPMENT ID | JOB NO. | DOCUMENT NO. | REV. |
|---|
| SUMMARY: |
|---|
© 2026 Inflection Point Engineering, LLC. All rights reserved. The content of this page — including calculation methods, reference data, written analysis, interactive tools, and source code — is the intellectual property of Inflection Point Engineering, LLC and is protected under applicable copyright, trademark, and trade secret laws. Unauthorized reproduction, redistribution, modification, or derivative use in whole or in part is prohibited without prior written consent.
Disclaimer. This material is provided for informational and educational purposes only and does not constitute professional engineering advice. Calculations, reference data, and methodologies are based on published standards and accepted engineering practice but are not a substitute for engineering judgment, site-specific analysis, or review by a licensed Professional Engineer. Inflection Point Engineering, LLC makes no warranties, express or implied, regarding the accuracy, completeness, or fitness for a particular purpose of any content presented here, and shall not be liable for any direct, indirect, incidental, or consequential damages arising from its use. Users assume all risk associated with applying this content to real-world design, operations, or decisions.
© 2026 Inflection Point Engineering, LLC. All rights reserved.