Section 4 — Structures and Foundations
IPE Engineering Practice IPE-EP-4-3-2C
Document number: IPE-EP-4-3-2C · Section: 4 — Structures and Foundations
THE MANUFACTURER OF EQUIPMENT PURCHASED BY REFINING COMPANY SHALL BE RESPONSIBLE FOR MEETING ALL APPLICABLE REQUIREMENTS OF THE ENGINEERING PRACTICES AND OTHER DOCUMENTS REFERENCED THEREIN REGARDLESS OF WHETHER THE ITEMS ARE INSPECTED BY A REPRESENTATIVE.
THE LATEST EDITION OF THE FOLLOWING STANDARDS AND PUBLICATIONS ARE REFERRED TO HEREIN.
EP 4-3-1 CONCRETE DESIGN
EP 4-3-2 CONCRETE CONSTRUCTION
EP 4-3-3 CONCRETE REINFORCED FABRICATION
LEVEL 2: PREFABRICATION MEETING, DOCUMENT REVIEW, REVIEW ITEMS, AND FINAL INSPECTION LEVEL 3: PREFABRICATION MEETING, DOCUMENT REVIEW, REVIEW ITEMS, WITNESS POINTS, AND FINAL
LEVEL 4: PREFABRICATION MEETING, DOCUMENT REVIEW, REVIEW ITEMS, WITNESS POINTS, HOLD POINTS, AND FINAL INSPECTION
| EQUIPMENT ID | JOB NO. | DOCUMENT NO. | REV. |
|---|
R CHECK: THE SHOP INSPECTOR SHALL REVIEW DOCUMENTED RESULTS OF INSPECTION PERFORMED BY VENDOR'S INSPECTION OR SUBCONTRACTED INSPECTOR.
W CHECK: INDICATES THE SHOP INSPECTOR SHALL WITNESS ITEM DURING FABRICATION. SHOP SHALL NOTIFY INSPECTOR TWO DAYS IN ADVANCE OF FABRICATION POINT BUT NEED NOT HOLD PRODUCTION FOR INSPECTION.
H CHECK: INDICATES THE SHOP INSPECTOR SHALL INSPECT ITEM DURING HOLD ON FABRICATION. SHOP SHALL NOTIFY INSPECTOR FIVE DAYS IN ADVANCE OF FABRICATION POINT AND SHALL NOT CONTINUE AFFECTED PRODUCTION UNTIL INSPECTOR PERFORMS INDICATED INSPECTION.
| R | W | H | INSPECTION/TESTING ACTIVITY | INSPECTOR'S INITIALS (REVIEW COMPLETE) | DATE |
|---|---|---|---|---|---|
| IDENTIFCATION OF REINFORCING STEEL PER EP 4-3-3: 5.2 | |||||
| DAMAGED REINFORCING REPLACED BY MANUFACTURER (EP 4-3-3: 5.3) | |||||
| REINFORCING STEEL MILL TESTS PROVIDED (EP 4-3-3: 5.4.2) | |||||
| CEMENT, AGGREGATE AND ADMIXTURES ACCEPTABLE (EP 4-6-1: 4.0) | |||||
| CONDITION OF REINFORCING ACCEPTABLE (EP 4-3-1: 4.6) | |||||
| SUB-GRADE ACCEPTABLE FOR CAST-AGAINST EARTH APPLICATIONS (EP 4-3-2: 4.1) | |||||
| FORMWORK ADEQUATELY PREPARED (EP 4-3-2: 4.2) | |||||
| ANCHOR BOLTS AND OTHER IMBEDDED ITEMS PROPERLY PLACED (EP 4-3-2: 5.2) | |||||
| CONDITION OF SITE ACCEPTABLE FOR CONCRETE PLACEMENT (EP 4-3-2: 7.1) | |||||
| CONCRETE SLUMP TESTS ACCEPTABLE (EP 4-3-2: 6.1.3) | |||||
| TEMPERATURE REQUIREMENTS FOR CONCRETING ACCEPTABLE (EP 4-3-2: 6.4) | |||||
| CONCRETE SAMPLED, TESTED, AND ACCEPTED (EP 4-3-2: 6.5) | |||||
| AIR CONTENT TEST RESULTS ACCEPTABLE (TABLE 3, EP 4- 3-1: 4.2) | |||||
| CONCRETE PLACEMENT PER REQUIREMENTS (EP 4-3-2: 7.2) | |||||
| CURING COMPLETED IN ACCORDANCE WITH REQUIREMENT (EP 4-3-2: 8.2) | |||||
| FORMS REMOVED AFTER ADEQUATE TIME (EP 4-3-2: 8.3) | |||||
| CONCRETE 28 DAY STRENGTH REQUIREMENTS MET (EP 4- 3-2: 6.5, EP 4-3-1: TABLE 1) | |||||
| FINAL INSPECTION OF CONCRETE ACCEPTABLE (EP 4-3-2: 8.4) | |||||
| AUTHORIZED WAIVERS AND/OR DEVIATIONS REVIEW | |||||
| REVIEW OF SUBORDERS OF UNPRICED PURCHASE ORDERS TOSUBVENDORS FOR COMPLIANCE WITH PRACTICES | |||||
| EQUIPMENT ID | JOB NO. | DOCUMENT NO. | REV. |
|---|
EP 4-3-2 C CONCRETE INSPECTION DAILY LOG SHEET
AS A MINIMUM, THE FOLLOWING LEVELS OF INSPECTION SHALL BE PERFORMED:
P CHECK: CHECK PRIOR TO STARTING WORK ON EACH SHIFT
R CHECK: IN ADDITION TO "P" CHECK, MAKE RANDOM CHECKS DURING SHIFT
| READINGS | READINGS | ||
|---|---|---|---|
| TIME | VALUE | ||
| R | AMBIENT TEMPERATURE (6.4, 7.2.7) | ||
| R | CONCRETE SLUMP (6.5) | ||
| R | AIR CONTENT (6.5) | ||
| P | CONDITIONS OF FORMS AND REINFORCEMENT PLACEMENT (4.2, 5.1, 5.2) |
||
| P | CONDITION OF SITE (4.1,7.1) | ||
| R | CONCRETE PLACEMENT (7.2) | ||
| R | SURFACE FINISH (8.1) | ||
| P | CURE TEMPERATURE (8.2) | ||
| INSPECTOR SIGN-OFF | INSPECTOR SIGN-OFF | INSPECTOR SIGN-OFF | INSPECTOR SIGN-OFF |
|---|---|---|---|
| INITIALS | NAME | COMPANY | SOCIAL SECURITY NUMBER |
| EQUIPMENT ID | JOB NO. | DOCUMENT NO. | REV. |
|---|
| SUMMARY: |
|---|
© 2026 Inflection Point Engineering, LLC. All rights reserved. The content of this page — including calculation methods, reference data, written analysis, interactive tools, and source code — is the intellectual property of Inflection Point Engineering, LLC and is protected under applicable copyright, trademark, and trade secret laws. Unauthorized reproduction, redistribution, modification, or derivative use in whole or in part is prohibited without prior written consent.
Disclaimer. This material is provided for informational and educational purposes only and does not constitute professional engineering advice. Calculations, reference data, and methodologies are based on published standards and accepted engineering practice but are not a substitute for engineering judgment, site-specific analysis, or review by a licensed Professional Engineer. Inflection Point Engineering, LLC makes no warranties, express or implied, regarding the accuracy, completeness, or fitness for a particular purpose of any content presented here, and shall not be liable for any direct, indirect, incidental, or consequential damages arising from its use. Users assume all risk associated with applying this content to real-world design, operations, or decisions.
© 2026 Inflection Point Engineering, LLC. All rights reserved.