Inflection Point Engineering Section 4 — Structures and Foundations

Concrete Construction Requirements

IPE Engineering Practice IPE-EP-4-3-2

Document number: IPE-EP-4-3-2 · Section: 4 — Structures and Foundations

SCOPE

2.0 REFERENCES

The latest edition of the following standards and publications are referred to herein.

STANDARDS AND PUBLICATIONS

IPE Engineering Practices
EP 1-1-3 Deviations to IPE Engineering Practices Reinforced EP 4-2-3 Concrete Foundations
EP 4-2-9 Grouting and Baseplates for Structural Steel and Equipment EP 4-3-1 Concrete Design
EP 4-3-3 Concrete Reinforcement Fabrication
ACI
211.1 Standard Practice for Selecting Proportions for Normal, Heavyweight and Mass Concrete
301 Specification for Structural Concrete for Buildings
304 Measuring, Mixing, Transporting and Placing Concrete
305 Recommended Practice for Hot Weather Concreting Recommended Practice for Cold Weather Concreting
308 Standard Practice for Curing Concrete
347 Recommended Practice for Concrete Formwork

STANDARDS AND PUBLICATIONS (CONT.)

ASTM
C31 Making and Curing Concrete Test Specimens in the Field
C39 Test for Compressive Strength of Cylindrical Concrete Specimens C94 Ready-Mixed Concrete
C143 Test for Slump of Portland Cement Concrete C150 Portland Cement
C172 Sampling Fresh Concrete
C173 Test for Air Content of Freshly Mixed Concrete by the Volumetric Method C231 Test for Air Content of Freshly Mixed Concrete by the Pressure Method
AWS
D1.4 Structural Welding Code, Reinforcing Steel
CRSI
MSP-2-81 Manual of Standard Practice

3.0

3.1

3.2

3.3

3.4

4.0

4.1

4.1.1

4.1.2

DEFINITIONS

Contractor - Company or business that agrees to furnish materials or perform specified services at a specified price and/or rate to the Owner.

Inspector - A Inflection Point Engineering, LLC appointed engineer or inspector. Owner - Inflection Point Engineering, LLC.

Owner's Engineer - A Inflection Point Engineering, LLC appointed engineer.

SUBGRADE PREPARATION AND FORMWORK

Foundation Subgrade Preparation

Excavations in materials shall be made with minimal disturbance of the bottom. All excavations shall be level, and free of loose material. The final work of excavating shall be completed just prior to the placing of the reinforcing steel and concrete.

All foundations shall be carried to good bearing soil and to the minimum depth below finish grade as indicated on the design drawings. If the requisite bearing is not encountered at the indicated minimum depth, or should over-excavation occur, the following shall be complied with:

REINFORCEMENT AND ANCHOR BOLTS

CONCRETE SELECTION PRODUCTION, AND TESTING

PLACING CONCRETE

FINISHING, CURING FORM REMOVAL. INSPECTION AND PATCHING

(*)Unless otherwise specified by the Owner, concrete surfaces shall be finished as follows:

9.0 TABLES

TABLE 1 RECOMMENDED SLUMPS

Types of Construction Slump in inches Slump in inches
Max. (1) Min.
Exposed Roof Slabs 2 1
Heavy Mass Construction 2 1
Pavements 3 1
Plain Footings 3 1
Reinforced Foundation Wall and Footings 3 1
Columns, Beams, Reinforced Walls, and Slabs 4 1

NOTE:

(1) (*)May be increased 1 inch for methods of consolidation other than vibration, if approved by the Owner's Engineer.

TABLE 2

MINIMUM COLD WEATHER TEMPERATURE

Air Temperature
°F (°C)
Minimum Concrete Temperature, °F Minimum Concrete Temperature, °F
For Sections with least dimension < 12 in. For Sections with least dimension  12 in.
30 to 40 (-1 to +4) 60 50
0 to 30 (-18 to -1) 65 55
Below 0 (-18) 70 60

TABLE 3 TESTING STANDARDS

Testing Requirements In Accordance With
Samples ASTM C172
Curing ASTM C31
Strength Testing ASTM C39
Slump Determination ASTM C143
Air Content ASTM C231 or C173

TABLE 4

MINIMUM AGE FOR SAFE REMOVAL OF FORMS - DAVS (2)

Construction Probable Mean Outside Temperature After
Period of Protection
Concrete Temperature During Protection Concrete Temperature During Protection Concrete Temperature During Protection Concrete Temperature During Protection
Construction Probable Mean Outside Temperature After
Period of Protection
50°F (10°C) 50°F (10°C) 70°F (21°C) 70°F (21°C)
Construction Probable Mean Outside Temperature After
Period of Protection
Type of Cement (ASTM C150) Type of Cement (ASTM C150) Type of Cement (ASTM C150) Type of Cement (ASTM C150)
Construction Probable Mean Outside Temperature After
Period of Protection
I, II or V Ill I, II or V lll
Pedestals, Walls, Column
and Other Vertical Above 32°F (0°C) 2 1 2 1
(or nearly vertical)
Sections (3)
25°F (-4°C) - 32°F (0°C) 11(1) 5(1) 8(1) 4(1)
16°F (9°C) - 25°F (4°F) 21(1) 16(1) 16(1) 12(1)
Below 16°F (-9°C) 29(1) 26(1) 23(1) 20(1)
Formed Grade Beams,
Elevated Slabs and Above 32°F (0°C) 6 3 4 3
Beams, Spans 120 in.
or Less
25°F (-4°C) - 32°F (0°C) 11 5 4 3
16°F (-9°C) - 25°F (-4°C) 21 16 16 12
Below 16°F (-9°C) 29 26 23 20
Spans Larger than 120 in. Above 32°F (0°C) 20 14 20 14
Spans Larger than 120 in. Below 32°F (0°C) 28 28 28 28

NOTE:

(*)ESTABLISHING FORM REMOVAL TIME

STEP 1: Perform a minimum of two compressive strength tests at each of the following time periods since casting (minimum of 6 total tests):

Type of Concrete Time after Casting (hours)
Normal, Type I or concrete with water- cement ratio < 0.5 24, 36 and 48
High Early Strength, Type III or concrete with water-cement ratio < 0.5 12, 18 and 36

STEP 2: Approximate the time required to achieve forty-percent of the 28-day compressive strength by least squares curve fitting of the data from Step 1. The data and all calculations shall be recorded in a format acceptable to the Owner's Engineer.

STEP 3: Round the time obtained in Step 2 to the next highest hour.

STEP 4: Perform two compressive strength tests at the time after casting obtained in Step 3.

STEP 5: If these tests indicate less than forty-percent of the 28-day compressive strength, add these data points to others obtained in this analysis and repeat Steps 2 through 4.

Otherwise, report this time as the minimum age for safe form removal.

NOTE: When using a concrete mix for which there is substantial field experience and data equivalent to what is required in this procedure, additional testing is not required.

TABLE 5

DOCUMENTATION REQUIREMENTS FOR CONCRETE CONSTRUCTION REQUIREMENTS PER EP 4-3-2

Item Description Format As-Built
1 Laboratory and field test results. Text N/A
2 Field inspection results. Text N/A
3 Data and calculations used to determine alternative minimum formwork removal time. Text N/A