Inflection Point Engineering Section 3 — Process Safety & Loss Prevention

Pressure Relieving System

IPE Engineering Practice IPE-EP-3-7-1

Document number: IPE-EP-3-7-1 · Section: 3 — Process Safety & Loss Prevention

SCOPE

2.0 REFERENCES

The latest edition of the following standards and publications are referred to herein.

STANDARDS & PUBLICATIONS

IPE Engineering Practices IPE Engineering Practices
EP 1–1–3 Deviations to IPE Engineering Practices
EP 3–7–2 Relief Disposal Systems
EP 3–7–3 Register of Pressure Relieving Systems
EP 3–7–4 Use of Protective Instrumentation in Pressure Relieving Systems
EP 5–1–1 General Piping Design
EP 5–3–14 Pressure Relief Valves
EP 5–3–15 Rupture Disk Devices
EP 5–6–2 Piping for Rotating Equipment
EP 5–6–4 Piping for Pressure Relief Systems
EP 5–6–8 Steam Tracing
EP 7–1–1 Pressure Vessels
EP 11–2–1 Fireproofing
EP 13–1–1 Power System Design Practices
EP 13–12–1 Electrical Tracing

STANDARDS & PUBLICATIONS (CONT.)

API Publications
RP520 Part I Sizing, Selection and Installation of Pressure–Relieving Devices in Refineries Part I – Sizing and Selection
RP520 Part II Sizing, Selection and Installation of Pressure–Relieving Devices in Refineries Part II – Installation
RP521 Guide for Pressure–Relieving and Depressuring Systems Std526 Flanged Steel Pressure–Relief Valves
Std2000 Venting Atmospheric and Low–Pressure Storage Tanks. (Nonrefrigerated and Refrigerated)
Std 2510 Design and Construction of Liquefied Petroleum Gas (LPG) Installations
ASME Codes
Sec VIII Pressure Vessels, Division 1
Sec VIII Pressure Vessels, Alternative Rules, Division 2 B31.3 Chemical Plant and Petroleum Refinery Piping

DEFINITIONS

SUMMARY OF PRESSURE RELIEF DESIGN PROCEDURE

The essential steps in the design of pressure relieving systems are summarized in this Section. Details of each step are given in other Sections of this Practice or other Practices as specified below.

All contingencies that may result in the overpressuring of equipment are considered, including external fire exposure of equipment, utility failures, equipment failures and malfunctions, abnormal processing conditions, thermal expansion, startup and shutdown, and operator error. Section 6.0 gives guidance as to the sources of overpressure that must be considered.

Using the P&ID’s (or PFD’s if not prepared) the plant or unit should be divided into related operational segments. Each segment should be small enough for the designer to track the impact of an upset, but large enough so that the impacts are contained within the segments being reviewed.

For each item of equipment in the segments, the overpressure cases to be considered should be used to identify the required individual relief loads. Section 7.0 provides guidance in determining relieving rates. The Summary of Relief Loads as described in EP 3–7–3 should be assembled during this step.

After the Summary of Relief Loads has been assembled, individual pressure relief devices are selected and sized. Sections 23.0 and 24.0 give guidance on the selection and sizing of pressure relief devices. Appendix D of API RP 520 Part 1 covers the requirements for sizing pressure relief devices when the relief is a flashing two–phase flow.

From the Summary of Relief Loads, common failure cases such as utility failures or the fire case are evaluated and the maximum relief requirement for each lead, lateral, subheader and main header of the common relief system can be determined. EP 3–7–2 gives guidance on the sizing and selection of the relief disposal system.

Once the pressure relief devices and disposal systems have been sized, there may be obvious mechanical design problems, such as excessively large header piping. If they exist, then the individual relief contributions should be examined in detail. Changes to the design, Section 28.0 of this Practice, should be explored to reduce individual relief loads where possible.

The final step in relief system design is to fully summarize and document the important details of the relief system per Section 29.0 of this Practice. EP 3–7–3 gives the requirements for the Register of Pressure Relieving Systems.

GENERAL DESIGN CONSIDERATIONS

CAUSES OF OVERPRESSURE

Operator error is considered as a potential cause of overpressure, although contingencies of operator error are generally not considered. The following are examples of operator error items which are generally not included:

In integrated plants, a process upset in one unit may have an effect on other units (e.g., loss of flow of a pumparound which is used as a source of heat for reboiling other towers). All possibilities such as these must be carefully considered and the potential for resulting overpressure evaluated.

Contingencies such as collapsed reactor bed vessel internals (e.g., fixed–bed reactor grids, coked catalyst beds, accumulation of catalyst fines, plugging of screens and strainers, lines blocked with coke, etc.), should be considered to identify any overpressure situations that could result.

(*) Overpressure as a result of reverse flow from a high–pressure system shall be considered. No credit shall be taken for the presence of a non–return valve or steam trap in a line unless a hazard quantification shows that the non–return valve, or trap, and the system have an acceptable failure rate. The acceptable failure rate will be specified by the Owner’s Engineer.

Not only design steady–state conditions, but also startup, shutdown, washout, regeneration, alternate feed stocks, blocked operations and other possible conditions must be evaluated for overpressure protection.

When increases in plant capacity are considered, the entire pressure relieving system should be reevaluated in accordance with plant Management of Change procedures. For example, a unit operating at 120% of design capacity may require additional pressure relieving capacity.

DETERMINATION OF INDIVIDUAL RELIEVING RATES

In situations where fluid flow stops due to failure of its utility supply, but is in parallel with equipment having a different energy source, credit may be taken for the unaffected and functioning equipment to the extent that operation is maintained and the operating equipment will not trip out due to overloading.

OPERATOR INTERVENTION CONSIDERATIONS

relief system design that incorporates Operator intervention. The proposed design, operating philosophy and PHA will also require the approval of the Operations Supervisor and the Owner's Engineer.

RELIEF DESIGN FOR LET–DOWN STATIONS

The circumstances should include all valves across the let–down station being open and gas breakthrough in liquid systems. Any bypass valves across the station should be assumed to be fully open and not simply to have the equivalent opening to normal process operation. This latter requirement may require smaller bypass valves or restriction orifices (in the case of existing plants) to be installed consistent with normal process flows. A detailed description of how to design for gas breakthrough is given in paragraph 9.16 of this Practice.

The designer shall consider the full range of operating conditions from purging, through prestart–up and start–up procedures to shut–down, regeneration and gas freeing. If there is a range of operating conditions, then the extreme case must be used in the calculation. The calculation of gas flow where gas breakthrough is possible should be based on gas at the normal operating conditions and properties, unless it is known that there are situations, for example at startup, where more arduous conditions are possible.

In designing the relief system, the size of the let–down valves is one of the limiting factors. It is vital that the installed valve size is reflected in the relief calculations and that the basis is clearly defined. Since the control valve trim size and the size of any orifice plate in the bypass are central to the relief case, this data should be listed with the pressure relief valve data as part of the relief system and should not be changed without appropriate resizing calculations in accordance with EP 3–7–3. In new plant design, control valve definition often comes late in the program. Relief valve checks must be made after control valve selection.

The HAZOP approach, is needed to specify the operating scenarios under which relief conditions including gas breakthrough could occur. Among these conditions there normally will be one scenario, for example at start–up, where the normal outlets in downstream equipment will be blocked, preventing any credit being allowed for the flow through these outlets.

In the design of relief systems on let–down stations in either vapor or liquid relieving situations, no credit shall be taken for operator intervention on the process plot.

Where conventional design leads to an impractical or grossly uneconomic solution, for example offshore or pipelines, then a high reliability protective instrumentation system may be considered as an alternative to providing liquid relief. Consideration should be given to minimizing the frequency and extent of the operation of relief valves. Any instrumentation (which is not high reliability) used for this purpose shall not contribute to a reduction in the design capacity of the relief system.

Relief design philosophy has considered, and still considers that it is unrealistic to design systems for simultaneous occurrence of two unrelated emergency conditions. The application of the thought processes included in the HAZOP approach often identifies that conditions which might otherwise be considered as separate have, in fact, a common cause. Such identification requires these conditions to be included in the design.

Since there can be appreciable temperature effects when hydrocarbon gases are reduced in pressure, the significance of these temperature changes need to be considered in both pressure relief valve sizing and the suitability of the materials of construction.

Normally in design, pipework lengths and valve sizes are such that the flow is determined by pressure drop through the valve rather than through the piping. However, this is not necessarily so in all retrofit cases and checks should be made. Where credit is to be taken for the influence of piping pressure drops, the relevant data needs to be recorded in the Register of Pressure Relieving Systems as described in EP 3–7–3.

EMERGENCY DEPRESSURING

THERMAL RELIEF

VACUUM RELIEF

COLD SERVICE

CREDIT FOR PROTECTIVE INSTRUMENTATION SYSTEMS

PRESSURE VESSELS

SHELL AND TUBE HEAT EXCHANGERS

AIR–COOLED HEAT EXCHANGERS

18.0 ROTATING EQUIPMENT

Pressure relief valve requirements for rotating equipment and piping associated with rotating equipment shall be in accordance with EP 5–6–2.

PROCESS AND UTILITY PIPING

PROCESS FIRED HEATERS

21.0 ATMOSPHERIC STORAGE TANKS

Pressure relieving arrangements for storage tanks to operate at or near atmospheric pressure shall be in accordance with API Std 2000.

22.0 LPG STORAGE

Pressure and vacuum relieving devices for LPG storage applications are stipulated in API Std 2510, Section 5.

PRESSURE RELIEF DEVICE SELECTION GUIDELINES

SIZING OF PRESSURE RELIEF DEVICES

ISOLATION OF PRESSURE RELIEF DEVICES

26.0 LOCATION OF PRESSURE RELIEF DEVICES

The location and arrangement of pressure relief devices shall be in accordance with EP 5–6–4.

27.0 INLET PIPING TO PRESSURE RELIEF DEVICES

The design and layout of inlet piping to pressure relief devices shall be in accordance with EP 5–6–4.

DESIGN MEASURES TO REDUCE RELIEF LOADS

DOCUMENTATION REQUIREMENTS FOR SYSTEM DESIGN

30.0 TABLES

TABLE 1

PRESSURES FOR SIZING RELIEF VALVES PER THE ASME CODE - SECTION VIII, DIVISION 1 OR 2

Conditions of Valve Arrangement Maximum Set Pressure Maximum Accumulation
Single Valve Installations P(1) 1.10P
Multiple Valve Installations First Valve
Additional Valves
Supplemental Valves (2)
P 1.05P
1.10P
1.16P
1.16P
1.21P
Valves sized for Fire Case
Single Valve Installation
P 1.21P
Valves sized for Fire Case Multiple Valve Installation
First Valve
Additional Valves
P 1.05P 1.21P
1.21P

NOTES:

FIGURES

Figure