Inflection Point Engineering Hydroprocessing Operations Guide

Turnaround Planning

Chapter from the Hydroprocessing Operations Guide.

HYDROPROCESSING TURNAROUND PLANNING

Turnaround Scope Checklist

Category Scope Item Frequency Duration Critical Path? Parallel Activities Notes
Reactor Catalyst changeout Every 2-5 years 10-20 days YES — longest single activity Exchanger cleaning, vessel inspection Plan early: catalyst ordering, dense loading crew
Reactor Reactor entry & inspection Every turnaround 3-5 days (per reactor) Yes if catalyst change Thermocouple replacement Confined space, H2S monitoring required
Reactor Distributor tray inspection/repair Every turnaround 2-3 days If catalyst is out Skin TC installation Critical for bed temperature distribution
Exchangers Bundle pull & cleaning Every turnaround 5-10 days Sometimes (large E/E) Reactor work, piping inspection Plan crane access, bundle storage area
Heater Tube inspection (UT, IRIS) Every turnaround 5-7 days Rarely (parallel to reactor) Burner maintenance, refractory repair Schedule heater work while reactor is open
Piping Inspection & repair Every turnaround Varies Rarely Other inspection activities Focus on high-consequence circuits
Vessels Separator, drum inspection Every turnaround 2-3 days each No (parallel work) Piping tie-ins, valve replacement Internals inspection, corrosion mapping
Instruments Loop checks, valve testing Pre-startup 5-10 days Yes — cannot start without Electrical checks, motor runs Start loop checks ASAP after mechanical completion
Rotating Equipment Compressor overhaul 2-5 year interval 10-15 days Sometimes (recycle comp) Alignment checks, coupling replacement Long-lead spare parts ordering critical

Pre-Turnaround Readiness Checklist

6 Months Before:
• Catalyst order placed and delivery confirmed
• Dense loading contractor contracted
• Scope of work finalized with inspection team
• Long-lead spare parts ordered (compressor parts, special valves)
• Safety plan and permit procedures reviewed

3 Months Before:
• Detailed schedule (Level 3 minimum) issued
• All materials on site or delivery dates confirmed
• Contractor mobilization plan finalized
• Equipment blind list prepared
• Pre-shutdown sampling and inspection complete

1 Month Before:
• Blind list walked down and verified
• All permits and safety documents reviewed
• Scaffold plan finalized
• Crane plan finalized (critical lifts identified)
• Communication plan issued (daily meetings, escalation path)

Shutdown Day:
• Controlled shutdown per operating procedure
• System depressured and cooled per catalyst vendor requirements
• Inert (N2 purge) before entry
• Blind installation per blind list
• Confined space gas testing before entry

Source: Hydroprocessing_Ops_Guide_v1.xlsx · sheet “Turnaround Planning”