Hydroprocessing Operations Guide
Chapter from the Hydroprocessing Operations Guide.
| Category | Scope Item | Frequency | Duration | Critical Path? | Parallel Activities | Notes |
|---|---|---|---|---|---|---|
| Reactor | Catalyst changeout | Every 2-5 years | 10-20 days | YES — longest single activity | Exchanger cleaning, vessel inspection | Plan early: catalyst ordering, dense loading crew |
| Reactor | Reactor entry & inspection | Every turnaround | 3-5 days (per reactor) | Yes if catalyst change | Thermocouple replacement | Confined space, H2S monitoring required |
| Reactor | Distributor tray inspection/repair | Every turnaround | 2-3 days | If catalyst is out | Skin TC installation | Critical for bed temperature distribution |
| Exchangers | Bundle pull & cleaning | Every turnaround | 5-10 days | Sometimes (large E/E) | Reactor work, piping inspection | Plan crane access, bundle storage area |
| Heater | Tube inspection (UT, IRIS) | Every turnaround | 5-7 days | Rarely (parallel to reactor) | Burner maintenance, refractory repair | Schedule heater work while reactor is open |
| Piping | Inspection & repair | Every turnaround | Varies | Rarely | Other inspection activities | Focus on high-consequence circuits |
| Vessels | Separator, drum inspection | Every turnaround | 2-3 days each | No (parallel work) | Piping tie-ins, valve replacement | Internals inspection, corrosion mapping |
| Instruments | Loop checks, valve testing | Pre-startup | 5-10 days | Yes — cannot start without | Electrical checks, motor runs | Start loop checks ASAP after mechanical completion |
| Rotating Equipment | Compressor overhaul | 2-5 year interval | 10-15 days | Sometimes (recycle comp) | Alignment checks, coupling replacement | Long-lead spare parts ordering critical |
6 Months Before:
• Catalyst order placed and delivery confirmed
• Dense loading contractor contracted
• Scope of work finalized with inspection team
• Long-lead spare parts ordered (compressor parts, special valves)
• Safety plan and permit procedures reviewed
3 Months Before:
• Detailed schedule (Level 3 minimum) issued
• All materials on site or delivery dates confirmed
• Contractor mobilization plan finalized
• Equipment blind list prepared
• Pre-shutdown sampling and inspection complete
1 Month Before:
• Blind list walked down and verified
• All permits and safety documents reviewed
• Scaffold plan finalized
• Crane plan finalized (critical lifts identified)
• Communication plan issued (daily meetings, escalation path)
Shutdown Day:
• Controlled shutdown per operating procedure
• System depressured and cooled per catalyst vendor requirements
• Inert (N2 purge) before entry
• Blind installation per blind list
• Confined space gas testing before entry
Source: Hydroprocessing_Ops_Guide_v1.xlsx · sheet “Turnaround Planning”
© 2026 Inflection Point Engineering, LLC. All rights reserved. The content of this page — including calculation methods, reference data, written analysis, interactive tools, and source code — is the intellectual property of Inflection Point Engineering, LLC and is protected under applicable copyright, trademark, and trade secret laws. Unauthorized reproduction, redistribution, modification, or derivative use in whole or in part is prohibited without prior written consent.
Disclaimer. This material is provided for informational and educational purposes only and does not constitute professional engineering advice. Calculations, reference data, and methodologies are based on published standards and accepted engineering practice but are not a substitute for engineering judgment, site-specific analysis, or review by a licensed Professional Engineer. Inflection Point Engineering, LLC makes no warranties, express or implied, regarding the accuracy, completeness, or fitness for a particular purpose of any content presented here, and shall not be liable for any direct, indirect, incidental, or consequential damages arising from its use. Users assume all risk associated with applying this content to real-world design, operations, or decisions.
© 2026 Inflection Point Engineering, LLC. All rights reserved.