Inflection Point Engineering FCC Operations Guide

Startup Sequence

Chapter from the FCC Operations Guide.

FCC STARTUP SEQUENCE OVERVIEW

Typical FCC Startup Steps

Phase Step Objective Key Parameters Duration Critical Checks Next Step Requires
1. Pre-startup Mechanical completion & punch All work complete, blinds removed Punchlist zero safety items Weeks Safety walk-down All items closed or accepted
2. Pre-startup Instrument loop checks Verify all instruments function Every loop in unit Days 100% completion Signed loop check sheets
3. Leak test Pressure test, leak check System integrity verification Test pressure, hold time 1-3 days Zero leaks on safety systems Successful hold test
4. Dry-out Regenerator refractory dry-out Remove moisture from refractory Ramp rate per refractory vendor 2-5 days Temperature ramp control Target temperature achieved and held
5. Catalyst loading Load catalyst inventory Fill regenerator to operating level Catalyst quality, level 1-2 days PSD, activity, metals on fresh catalyst Target inventory loaded
6. Circulation Establish catalyst circulation Verify circulation, slide valves, standpipes Catalyst flow, ΔPs, temperatures 4-8 hours Stable circulation, instrumentation OK Stable at target circulation rate
7. Heat-up Heat to operating temperature Bring regen and reactor to cracking temperature Torch oil or start-up burner 8-24 hours Ramp rate, uniform heating Regen >1,050°F, reactor >700°F
8. Feed introduction Introduce hydrocarbon feed Begin cracking operation Feed rate, temperatures, yields 2-4 hours Stable operation, no carryover Stable at minimum feed rate
9. Lined out Increase to design throughput Full rate operation All operating parameters 4-12 hours All parameters within limits Performance test conditions

Source: FCC_Operations_Guide_v1.xlsx · sheet “Startup Sequence”