Inflection Point Engineering Storage Tank Engineering Curriculum

Appurt

Module from the Storage Tank Engineering Curriculum curriculum.

Module 5 - Appurtenances · Learning Objectives · 1. Size shell nozzles per API 650 Table 5-6a/b reinforcement · 2. Specify gauging hatch, sample hatch, level gauges (servo, radar, displacer) · 3. Install roof vents: conservation vent (PVRV) + emergency pressure/vacuum · 4. Apply auto-gauging per IPE-EP-12-9-1 (tank gauging instrumentation) · 5. Provide manways per API 650 Sec 5.7 (shell manway, roof manway, 24 in typical) · Required Roof Vent Capacity (API 2000)

Flow Scenario Formula Value Notes Ref Period
Normal outbreathing (fill) B rate in/out 165 ft3/hr/ft3 flash Thermal + filling API 2000 4.1 Continuous
Normal inbreathing (empty) B rate in/out 94 ft3/hr/ft3 flash Thermal API 2000 4.1 Continuous
Thermal breathing f(D,H) Proportional tank volume Sun/nightfall API 2000 Table 2 Continuous
Emergency venting (fire) Q = 27,000 * A^0.82 Based on wetted area Fire exposure API 2000 Sec 5 Rare

Source: Storage_Tank_Engineering_Curriculum_v1.xlsx · Sheet: Appurt