Inflection Point Engineering Storage Tank Engineering Curriculum

API 653

Module from the Storage Tank Engineering Curriculum curriculum.

Module 9 - API 653 Inspection · Learning Objectives · 1. Apply API 653 monthly/external/internal inspection intervals · 2. Schedule external inspection every 5 years; internal every 10 or RBI · 3. Perform Magnetic Flux Leakage (MFL) on bottom plates during internal · 4. Measure settlement (differential, out-of-plane) per App B · 5. Complete fitness-for-service assessment per App B/App C for thin areas · API 653 Inspection Intervals

Inspection Type Max Interval Triggers Who Notes Ref
Routine monthly Monthly Per procedure Operator External walk-around API 653 6.3.1
External formal 5 yr Age & service Certified inspector Documented report API 653 6.3.2
UT shell thickness 5 yr or less Condition Certified or contracted CML UT readings API 653 6.3.3
Internal inspection 10 yr or Half RL Bottom CR Certified + services Floor scan MFL API 653 6.4
RBI-based Per risk Consequence/likelihood RBI team Extended possible API 580, API 653 6.4.2.2

Source: Storage_Tank_Engineering_Curriculum_v1.xlsx · Sheet: API 653