Inflection Point Engineering Project Controls and Estimation Curriculum

Turnaround

Module from the Project Controls and Estimation Curriculum curriculum.

Module 9 - Turnaround Cost and Schedule · Learning Objectives · 1. Break TA into Normal Work (planned), Scope Change (added), Emergent (found) · 2. Size mobilization (labor, scaffold, crane) for peak manloading · 3. Apply typical TA durations: 14-28 days for mid-unit; 35-45 days for FCC · 4. Benchmark TA cost: $5-15M for small unit, $50-200M for crude/FCC complete · 5. Track daily TA progress: open, earned hours, cost to date · Typical Turnaround Cost Breakdown

Category % of TA Cost Notes Variable or Fixed Peak Loading Ref
Labor (direct) 40-55% Welders, fitters, riggers Variable Peak mid-TA AACE
Materials 15-25% Gaskets, catalyst, spares Fixed by scope Mobilization AACE
Equipment rental 5-12% Cranes, scaffold Fixed Full TA AACE
Scaffolding 5-15% Setup + dismantle Fixed Peak construction AACE
Catalyst 5-20% HC + HDS + reformer Fixed Late TA Vendor
Engineering + PM 8-12% Planning + execution Fixed Pre + during AACE
Contingency 10-20% Emergent, growth Fixed (%) End AACE 40R
Other indirects 3-8% Utilities, insurance Fixed Full TA Owner

Source: Project_Controls_Estimation_Curriculum_v1.xlsx · Sheet: Turnaround