Inflection Point Engineering Project Controls and Estimation Curriculum

Estimate Class

Module from the Project Controls and Estimation Curriculum curriculum.

Module 3 - AACE Cost Estimate Classes · Learning Objectives · 1. Apply AACE Recommended Practice 18R-97 for process industry estimates · 2. Identify Class 5 (ROM), Class 4 (concept), Class 3 (budget), Class 2 (bid), Class 1 (definitive) · 3. Match class to project maturity (FEL phase) · 4. Understand expected range: Class 5 (-50/+100%), Class 1 (-5/+10%) · 5. Document basis of estimate (BOE) per AACE RP 34R-05 · AACE Estimate Class Matrix (RP 18R-97)

Class Maturity Accuracy Range Preparation Effort Typical Method Use
Class 5 0-2% -50 to +100% 0.005-0.5% TIC Capacity-factored ROM, FEL 1
Class 4 1-15% -30 to +50% 0.01-1% TIC Equipment-factored Budget, FEL 2
Class 3 10-40% -20 to +30% 0.1-3% TIC Semi-detailed Budget, FEL 3, FID
Class 2 30-70% -15 to +20% 0.5-10% TIC Detailed Bid, EPC start
Class 1 50-100% -10 to +15% 1-15% TIC Definitive Contract, change