Inflection Point Engineering Project Controls and Estimation Curriculum

Cost Methods

Module from the Project Controls and Estimation Curriculum curriculum.

Module 4 - Cost Estimating Methods · Learning Objectives · 1. Apply Lang factor method (factored from equipment cost) · 2. Use Hand method (module factors per equipment type) · 3. Apply Guthrie method (detailed factored per Module) · 4. Use Chilton/Page methods for onshore refinery · 5. Build detailed unit-rate estimate from MTO and crew productivity · Lang Factor Method (Solid-Fluid Refinery Typical)

Cost Category Factor of Equipment Notes Example (100M Eq) Running Total Ref
Delivered equipment 1.00 (base) Major equipment on site $100M $100M Guthrie
Equipment installation 0.25-0.40 Erection labor $30M $130M Guthrie
Piping 0.60-0.90 Pipe and supports $75M $205M Guthrie
Instrumentation 0.15-0.30 DCS + field $22M $227M Guthrie
Electrical 0.15-0.30 Power + control $22M $249M Guthrie
Civil / foundations 0.12-0.30 Concrete + steel $20M $269M Guthrie
Insulation and fireproofing 0.08-0.15 After piping $12M $281M Guthrie
Painting 0.03-0.08 Shop + field $5M $286M Guthrie
Subtotal direct 3.3x Inside battery limits $330M $430M Lang
Engineering + supervision 0.30-0.40 of direct Home office $100M $430M Lang
Construction expenses 0.10-0.15 of direct Scaffold + temp $40M $470M Guthrie
Contractor fee 0.05-0.10 of direct Profit + overhead $30M $500M Lang
Contingency 0.15-0.30 of subtotal Class 3 est $75M $575M AACE 40R

Source: Project_Controls_Estimation_Curriculum_v1.xlsx · Sheet: Cost Methods