Inflection Point Engineering Project Controls and Estimation Curriculum

Change Mgmt

Module from the Project Controls and Estimation Curriculum curriculum.

Module 8 - Change Management · Learning Objectives · 1. Distinguish trend (potential) from change order (approved) · 2. Apply PSM MOC for any physical, process, or procedure change · 3. Maintain baseline control (cost, schedule, scope) · 4. Approve changes at cost thresholds (management authority) · 5. Document all changes in change log with justification · Change Control Workflow

Step Action Artifact Approver Timeline Notes
1 Identify Potential change noticed Trend notice Project team Within days Monitor
2 Evaluate Cost + schedule impact Change evaluation Project controls 1 week Include contingency
3 Classify MOC or contractual Change request Engineering lead 1 week Safety implications
4 PHA MOC PHA if applicable MOC record PSM + PHA team Per program PSM required
5 Approve Per authority threshold Approved change order Owner + contractor Tier approval Budget impact
6 Baseline Update cost / schedule Revised baseline Project controls Immediate Replot S-curves
7 Communicate Notify all teams Revised documents Project manager Within days All stakeholders
8 Execute Implement change Construction / doc update Field / design Per change Track actual
9 Close Change complete Closeout change order Project controls At completion Lessons learned

Source: Project_Controls_Estimation_Curriculum_v1.xlsx · Sheet: Change Mgmt