Inflection Point Engineering Process Safety Management Curriculum

PSSR

Module from the Process Safety Management Curriculum curriculum.

Module 7 - Pre-Startup Safety Review (Element 10) · Learning Objectives · 1. Conduct PSSR for any new facility, major mod, or post-turnaround restart · 2. Verify equipment construction per spec and documentation · 3. Verify safety procedures, SOPs, and training complete · 4. Verify PHA recommendations addressed before startup · 5. Document PSSR completion and file (auditable) · PSSR Checklist Categories

Category Key Items Complete? Who Notes Ref
Mechanical P&IDs updated, hydrotest passed, NDE records Yes/No Inspector Docs 1910.119(i)
E&I DCS loops tested, alarms verified, SIF tested Yes/No E&I Alarms 1910.119(i)
Process SOPs updated, limits set, feeds ready Yes/No Process Docs 1910.119(i)
PSM PHA reviewed, MOC closed, training done Yes/No PSM manager Evidence 1910.119(i)
Safety Fire protection, emergency lighting, HVAC Yes/No Safety Systems functional 1910.119(i)
Environmental Permits valid, monitoring in place Yes/No Env Compliance 1910.119(i)
Startup sequence Step-by-step confirmed Yes/No Ops Readiness 1910.119(i)

Source: Process_Safety_Management_Curriculum_v1.xlsx · Sheet: PSSR