Commissioning and Startup Training Curriculum
Module from the Commissioning and Startup Training Curriculum curriculum.
Module 7 — Utilities Commissioning · Learning Objectives · 1. Commission steam system from boiler to users including superheater warm-up and condensate recovery. · 2. Start up cooling water system with correct chemical treatment and biocide dosing. · 3. Commission instrument and plant air systems to target dew point and pressure. · 4. Inert system with N2 and verify oxygen levels prior to hydrocarbon introduction. · 5. Commission fuel gas and flare systems with purge and pilot verification. · Utility Commissioning Order
| Order | Utility | Rationale |
|---|---|---|
| 1 | Plant air | Powers instrumentation and valves |
| 2 | Instrument air | Required before DCS loop live |
| 3 | Nitrogen | Needed to inert HC systems |
| 4 | Cooling water | Required before heat input |
| 5 | Steam | Requires CW for turbines and condensers |
| 6 | Fuel gas | Requires N2 inerting done |
| 7 | Flare | Must be live before HP HC lines pressurize |
| Steam Commissioning Steps | ||
| Step | Action | |
| 1 | Boil out boiler with alkaline solution (TSP/Na2CO3, 212 °F, 24 hr) | |
| 2 | Drain, flush, refill with treated BFW | |
| 3 | Raise pressure slowly to ~15% design; blowdown | |
| 4 | Raise to design, warm header via bypass, drain condensate | |
| 5 | Steam blow piping per Module 3 | |
| 6 | Back in-service: slowly crack supply valves, watch temperature | |
| 7 | Place PRVs in service per set pressure tiering | |
| Cooling Water Commissioning | ||
| Step | Action | |
| 1 | Fill tower basin with treated water | |
| 2 | Start makeup / blowdown control | |
| 3 | Start CW pumps; verify net flow | |
| 4 | Dose corrosion inhibitor, dispersant, biocide | |
| 5 | Verify chemistry: pH 7.5–9.0, conductivity, ORP for biocide | |
| 6 | Chlorine / bromine residual target 0.3–0.5 ppm | |
| 7 | Pass water through all users sequentially | |
| Nitrogen Inerting Criteria | ||
| Service | Target O2 | |
| Hydrocarbon vessel — pre-feed | <1.0 vol% | |
| Reactor loop — pre-H2 | <0.5 vol% | |
| Cryogenic service | <10 ppmv O2 | |
| Hydrogen service | <200 ppmv O2 | |
| Lube oil reservoir blanket | <4.0 vol% (hot work) | |
| Instrument Air Specifications | ||
| Parameter | Spec | |
| Pressure | 90–125 psig typical, ISA-7.0.01 | |
| Dew point | -40 °F (<10 ppm H2O) at line pressure | |
| Particle | <40 µm | |
| Oil | <1 ppmw | |
| Flow margin | 20% above peak design | |
| Flare Commissioning | ||
| Item | Check | |
| Purge gas | N2 or FG at minimum velocity to prevent air ingress | |
| Pilot flame | All pilots lit and confirmed at ground panel | |
| Thermocouple | Each pilot TC reading >300 °F | |
| Seal drum | Water level maintained, auto-makeup | |
| KO drum | Empty, LT working, pump-out aligned | |
| Relief valve lineup | All PSVs lined up to flare before pressurization | |
| ◄ Return to Instructions |
Source: Commissioning_and_Startup_Training_Curriculum_v1.xlsx · Sheet: Mod 7 - Utilities
© 2026 Inflection Point Engineering, LLC. All rights reserved. The content of this page — including calculation methods, reference data, written analysis, interactive tools, and source code — is the intellectual property of Inflection Point Engineering, LLC and is protected under applicable copyright, trademark, and trade secret laws. Unauthorized reproduction, redistribution, modification, or derivative use in whole or in part is prohibited without prior written consent.
Disclaimer. This material is provided for informational and educational purposes only and does not constitute professional engineering advice. Calculations, reference data, and methodologies are based on published standards and accepted engineering practice but are not a substitute for engineering judgment, site-specific analysis, or review by a licensed Professional Engineer. Inflection Point Engineering, LLC makes no warranties, express or implied, regarding the accuracy, completeness, or fitness for a particular purpose of any content presented here, and shall not be liable for any direct, indirect, incidental, or consequential damages arising from its use. Users assume all risk associated with applying this content to real-world design, operations, or decisions.
© 2026 Inflection Point Engineering, LLC. All rights reserved.