Inflection Point Engineering Commissioning and Startup Training Curriculum

Mod 7 - Utilities

Module from the Commissioning and Startup Training Curriculum curriculum.

Module 7 — Utilities Commissioning · Learning Objectives · 1. Commission steam system from boiler to users including superheater warm-up and condensate recovery. · 2. Start up cooling water system with correct chemical treatment and biocide dosing. · 3. Commission instrument and plant air systems to target dew point and pressure. · 4. Inert system with N2 and verify oxygen levels prior to hydrocarbon introduction. · 5. Commission fuel gas and flare systems with purge and pilot verification. · Utility Commissioning Order

Order Utility Rationale
1 Plant air Powers instrumentation and valves
2 Instrument air Required before DCS loop live
3 Nitrogen Needed to inert HC systems
4 Cooling water Required before heat input
5 Steam Requires CW for turbines and condensers
6 Fuel gas Requires N2 inerting done
7 Flare Must be live before HP HC lines pressurize
Steam Commissioning Steps
Step Action
1 Boil out boiler with alkaline solution (TSP/Na2CO3, 212 °F, 24 hr)
2 Drain, flush, refill with treated BFW
3 Raise pressure slowly to ~15% design; blowdown
4 Raise to design, warm header via bypass, drain condensate
5 Steam blow piping per Module 3
6 Back in-service: slowly crack supply valves, watch temperature
7 Place PRVs in service per set pressure tiering
Cooling Water Commissioning
Step Action
1 Fill tower basin with treated water
2 Start makeup / blowdown control
3 Start CW pumps; verify net flow
4 Dose corrosion inhibitor, dispersant, biocide
5 Verify chemistry: pH 7.5–9.0, conductivity, ORP for biocide
6 Chlorine / bromine residual target 0.3–0.5 ppm
7 Pass water through all users sequentially
Nitrogen Inerting Criteria
Service Target O2
Hydrocarbon vessel — pre-feed <1.0 vol%
Reactor loop — pre-H2 <0.5 vol%
Cryogenic service <10 ppmv O2
Hydrogen service <200 ppmv O2
Lube oil reservoir blanket <4.0 vol% (hot work)
Instrument Air Specifications
Parameter Spec
Pressure 90–125 psig typical, ISA-7.0.01
Dew point -40 °F (<10 ppm H2O) at line pressure
Particle <40 µm
Oil <1 ppmw
Flow margin 20% above peak design
Flare Commissioning
Item Check
Purge gas N2 or FG at minimum velocity to prevent air ingress
Pilot flame All pilots lit and confirmed at ground panel
Thermocouple Each pilot TC reading >300 °F
Seal drum Water level maintained, auto-makeup
KO drum Empty, LT working, pump-out aligned
Relief valve lineup All PSVs lined up to flare before pressurization
◄ Return to Instructions

Source: Commissioning_and_Startup_Training_Curriculum_v1.xlsx · Sheet: Mod 7 - Utilities