Inflection Point Engineering Commissioning and Startup Training Curriculum

Mod 4 - Pressure Testing

Module from the Commissioning and Startup Training Curriculum curriculum.

Module 4 — Pressure and Tightness Testing · Learning Objectives · 1. Plan and execute hydrostatic testing per ASME B31.3 / ASME Section VIII requirements. · 2. Select between hydrotest, pneumatic test, and sensitive leak test based on service and risk. · 3. Calculate test pressure including temperature correction factor. · 4. Apply safe work practices for pneumatic testing stored energy hazards. · 5. Verify tightness with soap, ultrasonic, or helium leak detection techniques. · Test Methods

Method Code Basis Use Case
Hydrotest ASME B31.3 §345.4 / ASME VIII UG-99 Default for pressure piping/vessels
Pneumatic ASME B31.3 §345.5 Water-sensitive or water-removal-impractical
Sensitive leak (bubble) ASME V Art. 10 Tightness; new joints and seals
Helium mass spec ASME V Art. 10 App. IV Cryogenic, high-integrity seal systems
Service leak test ASME B31.3 §345.7 Combined with startup for Cat. D fluid service
Initial service leak ASME B31.3 §345.7 Low-hazard category D only
Hydrotest Pressure Calculation (B31.3)
Parameter Formula
Test pressure minimum P_T = 1.5 × P × (S_T / S)
P Design gauge pressure, psig
S_T Allowable stress at test temperature
S Allowable stress at design temperature
Max ratio cap (S_T/S) capped at 6.5
Example CS A106-B, P=300 psig, ratio=1.0 → P_T = 450 psig
Pneumatic Test — Safety Requirements
Item Requirement
Test pressure 1.1 × design, ASME B31.3 §345.5.4
Initial pressurization 25 psig hold; examine joints
Pressure increments 50% target → 100%
Exclusion zone Calculated energy zone — typical 200–500 ft
Relief device Set ≤ 110% of test pressure
Stored energy E = (P×V)/0.2 × [1 − (Patm/P)^0.286]
Personnel Clear all non-essential; remote read
Hydrotest Procedure
Step Action
1 Install blind flanges / isolation
2 Review test pkg: P&ID markup, test boundary, relief
3 Fill from low point; vent all high points
4 Pressurize to 50%; hold 10 min; inspect
5 Raise to 100% test pressure; hold 10 min minimum
6 Reduce to design pressure; walk and inspect joints
7 Drain, dry, remove blinds, reinstate lines
Tightness Test Acceptance
Test Acceptance
Soap bubble No continuous bubbling at 1.1 × P
Ultrasonic No signal above background
Helium mass spec Leak rate ≤ 1e-6 std cc/s
Pressure decay <1% of abs pressure over 24 hr (T-corrected)
Vacuum decay <2 mbar/hr
Common Problems
Symptom Cause Fix
Pressure drift Temperature change Correct using ideal gas law; re-time
Slow leak at flange Low bolt torque Re-torque per spec, dont overtorque
Gasket leak Wrong gasket material Replace with spec gasket (spiral wound)
Weld leak Porosity Excavate, re-weld, re-NDE
Test water retention No low-point drain Install temporary drain; N2 purge
◄ Return to Instructions

Source: Commissioning_and_Startup_Training_Curriculum_v1.xlsx · Sheet: Mod 4 - Pressure Testing