Inflection Point Engineering Commissioning and Startup Training Curriculum

Mod 2 - MC & Punch Lists

Module from the Commissioning and Startup Training Curriculum curriculum.

Module 2 — Mechanical Completion & Punch Lists · Learning Objectives · 1. Execute system-by-system mechanical completion walkdowns. · 2. Classify punch list items per A/B/C severity and assign closure responsibility. · 3. Manage the punch list database through clearance, transfer, and closeout. · 4. Sign off MC certificates with correct supporting documentation. · 5. Recognize common MC delays and apply mitigation strategies. · Punch List Categorization

Category Definition Impact Timing
A Must correct before system energization/pressurization Safety / Operability Before Pre-Comm start
B Must correct before startup but not blocking pre-comm Startup readiness Before feed-in
C Cosmetic / non-critical Aesthetic / minor After startup, in 90 days
MC Walkdown Checklist — Piping
Item Check Reference
Line class conformance Spec-break tagged, correct material P&ID / line list
Slope / pocket Gravity drains, no pockets where spec requires Isometric
Supports / shoes Installed, correct offset Support drawing
Spring hangers Pin in travel stop Spring table
Blinds / spades Correct orientation, per P&ID P&ID
Vents / drains Present, capped, tagged P&ID
Insulation Correct thickness, jacket intact Spec
PWHT records Hardness surveys done for CrMo WPS / PQR
MC Walkdown Checklist — Vessels / Columns
Item Check
Internals installed Trays, packing, demister per internals drawing
Manway closure All bolts torqued, gaskets correct
Relief valves Tag, set pressure, seal, inlet/outlet orientation
Nozzle projection Within tolerance, no interference
Ladder / platform Welded, grated, toe-boards in place
Nameplate Installed, legible
NDE records Final UT/RT per code stamp
Common MC Delays
Cause Mitigation
Missing vendor data books Require MDR at 90% progress
Instrument cabling not dressed Schedule electrical finish trails pipe
Late arrival of small-bore piping Expedite with second source
Insulation not complete Split-box insulation to commissioning scope
Relief valve bench test delayed Use spare certified valves
MC Certificate — Required Attachments
Document Source
Redlined P&ID Construction markup
Punch list with signoffs Punch list database export
NDE summary QC records
Hydrotest package Ready for Mod 4
PWHT / heat-treat records QC
Weld map / heat number traceability QC
Vendor data books EPC document control
◄ Return to Instructions