Inflection Point Engineering Commissioning and Startup Training Curriculum

Mod 11 - Perf Test & Handover

Module from the Commissioning and Startup Training Curriculum curriculum.

Module 11 — Performance Test and Handover · Learning Objectives · 1. Plan and execute licensor performance test runs per defined protocol. · 2. Apply ASME PTC test codes for utility and rotating equipment performance. · 3. Close out commissioning punch lists to the agreed thresholds. · 4. Execute care-and-custody transfer of the asset to Operations. · 5. Capture lessons learned and release commissioning team. · Test Protocols

Test Reference Duration
Unit guarantee run Licensor test protocol 72 hr typical (hydrocracker / hydrotreater)
Fired heater performance API 560 / ASME PTC 4 12 hr steady
Centrifugal compressor ASME PTC 10 4 hr per test point
Steam turbine ASME PTC 6 Per vendor
Cooling tower ASME PTC 23 24 hr
FCC regen Licensor 7-day heat balance
Pre-Test Requirements
Item Check
Instrumentation Recently calibrated, traceable
Custody meters Proven within last 30 days
Steady state No MOCs open on unit; rate steady ±2%
Feed spec Within design slate range
Product disposition No recycle; on-spec product on draw
Test team Licensor, owner, EPC present with signed protocol
Test Data Required
Category Example
Feed Rate, density, S, N, distillation
Product Yields, properties, spec compliance
Utilities Steam, fuel gas, power, CW, N2 usage
Emissions NOx, SOx, CO, VOC per permit
Reliability No trips, alarms above threshold
Losses Flare vol, slop, off-spec
Punch List Closeout
Category Target at Handover
A Zero outstanding
B Zero outstanding OR documented transfer to Ops with funding
C Transferred to Ops backlog with owner
Documentation All vendor manuals, as-builts, loop folders in DMS
Training Operator sign-off on unit-specific SOPs
Spares Critical spares in warehouse with BoM
Care & Custody Transfer
Item Action
Certificate of completion Issued by EPC
Acceptance certificate Signed by Operations Manager
Warranty period Start date locked; typ. 12–24 months
Snag list B/C items with tracking number
Insurance Transferred from construction to operations
LOTO / access Keys transferred; work permits under Ops system
Lessons Learned Capture
Category Example Entry
Schedule Cleaning scope underestimated — allow +2 weeks
Technical Loop check missed valve signal reversal on 3 FICs
Safety Near miss during N2 purge — install O2 monitors earlier
Quality Vendor data books late — tighten vendor milestones
Commercial Change orders from field modifications — MOC discipline
◄ Return to Instructions

Source: Commissioning_and_Startup_Training_Curriculum_v1.xlsx · Sheet: Mod 11 - Perf Test & Handover